1 |
Ongoing |
Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenok-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (from Km 0.00 to Km 13.00 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal) PKG- IVA |
15.24 |
402.94 |
01-03-2019 |
04-10-2019 |
99 |
74 |
03-04-2022 |
31-12-2025 |
|
N Siva Prakash Reddy (NSPR) Constr. (I) Pvt. Ltd. - Vinod Kumar Jain (VKJ) (JV) |
nsprvkj.bagrakot@gmail.com |
2 |
Ongoing |
Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenock-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (from Km 13.00 to Km 25.60 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal) PKG- IVB |
12.60 |
295.97 |
19-08-2020 |
05-10-2020 |
96 |
94 |
05-04-2023 |
31-10-2025 |
|
Rani Constructions Pvt. Ltd. - Sri Satya Sai Infrastructrue Pvt. Ltd. (JV) |
nh717a.4b@ranigroup.com |
3 |
Ongoing |
Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of sect. from Pedong bypass to Reshi Border km 79.700 to km 96.254 of NH-717A under SARDP-NE-A on EPC (Lava More-Reshi Border ) Pkg-VB as part of Alternate connectivity to Gangtok. |
16.55 |
395.59 |
24-07-2020 |
20-10-2020 |
91 |
88 |
17-04-2022 |
31-10-2025 |
|
TTC Infra India - Suryodaya Infra Projects Pvt Ltd (SIPL) (JV) |
ttc.prpkgvb@gmail.com |
4 |
Ongoing |
Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of Kafer- Lava More section from km 40.00 to km 61.100 of NH717-A on EPC under SARDP-NE A in state of West Bengal (Pkg-VA) |
21.10 |
273.78 |
21-08-2020 |
05-10-2020 |
95 |
93 |
05-04-2023 |
31-10-2025 |
|
Rani Constructions Pvt. Ltd. - Sri Satya Sai Infrastructrue Pvt. Ltd. (JV) |
nh717a.5a@ranigroup.com |
5 |
Completed |
Construction of Mechi bridge (of 675m) and Approaches of 2/4-Lane with paved shoulder on NH-327B across Indo-Nepal border on Asian Highway (AH -02) by ADB fund under SASEC Tranche-2 on EPC mode |
1.50 |
158.65 |
23-11-2017 |
01-02-2018 |
100 |
100 |
30-01-2021 |
|
05-09-2020 |
Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) |
draiplmechi@gmail.com |
6 |
Completed |
Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenock-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (Package No. IVD from Km 26.10 to 40.00 of Bagrakot - Kafer section of NH 717A on EPC Mode under Phase A of SARDP-NE in the State of West Bengal) PKG- IVD |
13.90 |
242.97 |
20-03-2020 |
11-06-2020 |
100 |
99 |
10-06-2022 |
|
02-01-2024 |
Ketan Construction Ltd.(KCL)-Bhutan Builders Pvt. Ltd.(BBPL) (JV) |
kclbbpl2020@gmail.com |