Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion/ Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of sect. from Pedong bypass to Reshi Border km 79.700 to km 96.254 of NH-717A under SARDP-NE-A on EPC (Lava More-Reshi Border ) Pkg-VB as part of Alternate connectivity to Gangtok. 16.55 395.59 24-07-2020 20-10-2020 91 88 17-04-2022 31-10-2025 TTC Infra India - Suryodaya Infra Projects Pvt Ltd (SIPL) (JV) ttc.prpkgvb@gmail.com
2 Ongoing Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of Kafer- Lava More section from km 40.00 to km 61.100 of NH717-A on EPC under SARDP-NE A in state of West Bengal (Pkg-VA) 21.10 273.78 21-08-2020 05-10-2020 95 93 05-04-2023 31-10-2025 Rani Constructions Pvt. Ltd. - Sri Satya Sai Infrastructrue Pvt. Ltd. (JV) nh717a.5a@ranigroup.com
3 Ongoing Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenock-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (from Km 13.00 to Km 25.60 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal) PKG- IVB 12.60 295.97 19-08-2020 05-10-2020 96 94 05-04-2023 31-10-2025 Rani Constructions Pvt. Ltd. - Sri Satya Sai Infrastructrue Pvt. Ltd. (JV) nh717a.4b@ranigroup.com
4 Ongoing Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenok-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (from Km 0.00 to Km 13.00 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal) PKG- IVA 15.24 402.94 01-03-2019 04-10-2019 99 74 03-04-2022 30-06-2025 N Siva Prakash Reddy (NSPR) Constr. (I) Pvt. Ltd. - Vinod Kumar Jain (VKJ) (JV) nsprvkj.bagrakot@gmail.com
5 Completed Construction of Mechi bridge (of 675m) and Approaches of 2/4-Lane with paved shoulder on NH-327B across Indo-Nepal border on Asian Highway (AH -02) by ADB fund under SASEC Tranche-2 on EPC mode 1.50 158.65 23-11-2017 01-02-2018 100 100 30-01-2021 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) draiplmechi@gmail.com
6 Completed Strengthening/Restoration of existing road from km 76.350 to km 79.700 of NH-717A [i.e, start of Pedong Bypass to Rishi Border) in the State of West Bengal on EPC Mode (Pkg- VB)(i)] 3.35 5.30 08-06-2021 26-07-2021 100 100 21-01-2022 Vishwas
Construction Co. Ltd
vishwas.pedong@gmail.com
7 Completed Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenock-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (Package No. IVD from Km 26.10 to 40.00 of Bagrakot - Kafer section of NH 717A on EPC Mode under Phase A of SARDP-NE in the State of West Bengal) PKG- IVD 13.90 242.97 20-03-2020 11-06-2020 100 99 10-06-2022 Ketan Construction Ltd.(KCL)-Bhutan Builders Pvt. Ltd.(BBPL) (JV) kclbbpl2020@gmail.com