Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion/ Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Construction, Operation & Maintenance of 2-L Bi-directional Silkyara Bend- Barkot Tunnel with escape passage including approaches (Tunnel-4.531 & Approach road- 0.328) on Dharasu-Yamunotri section b/w Chainage 25.400km and 51.00km falling along NH-134 (Old NH-94) on EPC mode
Silkyara Side (South Portal) & Barkot Site (North Portal)
4.86 1383.78 31-05-2018 09-07-2018 64 64 08-07-2022 30-09-2026 Navayuga Engineering Co. Limited necdocumentcontroller@gmail.com nec@navayuga.com
2 Ongoing Construction for Mitigation Measures of 5 Nos. Landslides, 5 Nos. Sinking Zones in between Ch. 433.00 to 450.00 (BANERPANI VILLAGE) on NH-07 on EPC mode in the state of Uttarakhand (Package-2) 1.99 259.64 15-03-2024 16-12-2024 20 18 15-06-2026 08-06-2026 SRM Contractors Ltd. srmcontractors@gmail.com
srmslope@gmail.com
3 Ongoing Construction for Mitigation Measures of 10 Nos. Landslides, 01 No. Sinking Zones and 1 No. of Minor Bridge in between at Ch. Km 368.00 to Km 433.00 on NH-07 on EPC (Package-1) 1.69 216.68 15-03-2024 14-06-2024 79 73 14-12-2025 05-12-2025 Bharat Constructions (India) Pvt. Ltd. bciplnhidclpkg01kpg@gmail.com
4 Ongoing Construction for Mitigation Measures of 5 Nos. Landslides, 5 Nos. Sinking Zones and 1 No. of Minor Bridge in between at Ch. Km 450.00 to Km 468.00 on NH-07 on EPC (Package-3) 1.46 250.33 15-03-2024 14-06-2024 49 48 14-12-2025 05-12-2025 RSB Projects Pvt. Ltd. - SRM Contractors Ltd. (JV) srmcontractors@gmail.com
srmslope@gmail.com
5 Completed Construction of Road and Slope Protection works at Gholteer Landslide from km. 379.100 to km. 380.275 of NH-07 under “Chardham Pariyojna” 1.18 89.27 10-12-2018 03-05-2019 100 100 02-05-2020 Bharat Constructions (India) Pvt. Ltd. bharatconstruction248@gmail.com
6 Completed Rehabilitation/ treatment of landslide location with slope protection work and drainage improvement at Nandprayag (Km 420.400), Maithana (km 423.500), Birahi (km 437.400) & Gulabkoti (Km 464.400) on NH-58 with proposed length of 200m, 350m, 100m & 125m respectively in Chamoli district 0.78 57.66 06-04-2016 04-11-2016 100 100 06-05-2018 R.G. Buildwell Engineers LTD. uk.package@gmail.com
7 Completed Construction and upgradation of existing road to 2-lane with paved shoulder from km 399.000 to km 430.000 of karanprayag to chamoli (excluding km 420.250 to km 420.500 and km 423.300 to 423.650) of NH-07 under Chardham Pariyojana on EPC basis under NH(O) (Package-2) 28.80 403.36 26-03-2018 24-05-2018 99 98 21-11-2020 Shivalaya Construction co. Pvt. Ltd. (SCCPL) - Hillways Construction Company Pvt. Ltd. (HCCPL) (JV) scclhccpljv@rediffmail.com
8 Completed Construction of Road, Bridge and Slope Protection Gallery works of Landslide at Barethi (Ex. Km. 100.300 to km 101.060) of Section NH-34 in the State of Uttarakhand on EPC 0.76 40.89 18-09-2017 04-01-2018 100 100 03-01-2020 Bharat Constructions (India) Pvt. Ltd. bharatconstruction248@gmail.com
9 Completed Construction and Upgradation of existing road to 2-lane with paved shoulder and Slope Protection Work (450m) & Patalganga Tunnel of (150 m) from existing Km. 458.900 to Km. 459.475 (Design Ch. 456.200 to Ch. 456.800) of Patalganga Landslide of NH-07 under “Chardham Pariyojna” on EPC basis in the state Uttarakhand. 0.60 45.37 10-12-2018 03-05-2019 100 100 02-05-2020 Bharat Constructions (India) Pvt. Ltd. bharatconstruction248@gmail.com
10 Completed Rehabilitation/ Treatment of Landslide location with slope protection and Drainage improvement at Helang (Km 468.200), Govindghat-II (Km 497.000) and Govindghat-III (km 500.000) on Rudraprayag-Mana section on NH-58 (New NH 07) with proposed length of 275m, 150m & 150m respectively in Chamoli District 0.58 45.09 06-04-2016 04-11-2016 100 100 31-01-2020 R.G. Buildwell Engineers LTD. uk.package@gmail.com
11 Completed Construction and Upgradation of existing road to 2-lane with paved shoulder from Km 430.000 to Km 468.000 of Chamoli to Paini (excluding Km 437.625 to Km 437.775, Km 458.900 to Km 459.475 and Km 464.425 to Km 464.525) of NH-07 under Chardham Pariyojana on EPC basis under NH(O) (Package-3) 36.68 417.24 26-03-2018 23-05-2018 100 99 20-11-2020 NKG Infrastructure Pvt. Ltd. nkg@nkgindia.com
12 Completed Construction of valley side slope stabilization treatment including drainage, cross drainage work and pavement in Dharasu- Gangotri road from km. 123.080 to km 123.970 of NH-34 and stabilization of dumping zone 0.89 23.51 22-11-2019 08-01-2020 100 100 05-07-2020 Chaudhary Construction Company Pvt Ltd. ccc.nhidcldharasupm@gmail.com
13 Completed Construction and upgradation of existing road to 2-lane with paved shoulder from Km 368.000 to Km 399.000 of Lameri to Karanprayag (Excluding km 379.000 to km 380.275) of NH-07 under Chardham Pariyojana on EPC basis under NH(O) (Package-I) 29.13 274.31 26-03-2018 23-05-2018 100 100 20-11-2020 RCC Developers ltd rccd109@gmail.com
14 Completed Protection works at Nalupani Landslide (Ex. Km 123.080 to km 123.480, Km. 123.665 to Km. 123.740 and Km. 123.770 to Km. 123.970) Section of NH-34 in the State of Uttarakhand 0.74 47.13 16-06-2017 11-09-2017 100 100 15-03-2019 KCC Buildcon Pvt. Ltd. kcc.dharsu@gmail.com