Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion/ Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Construction of 2-lane specification road with paved shoulder as realignment (Greenfield alignment) of existing stretch on NH-510 between Legship - Gyalshing from km58.840 to km75.00 under SARDP-NE Phase “A” on EPC mode (Pkg- V) 16.16 414.20 14-09-2020 10-11-2020 49 44 09-05-2023 31-12-2026 JRA Infrastructure Ltd. (JRAIPL) jra.ahmedabad@gmail.com
2 Ongoing Construction of 2-laning with Paved Shoulder of New Greenfield alignment from Chochenpheri at Km 52+000 to Helipad near Menla at Km 82+000 of Rhenock- Menla Spur under SARDP-NE Phase 'A' on NH-717B (Pkg-III A) 30.00 786.60 28-10-2020 10-12-2020 51 46 09-12-2023 31-12-2026 U.P. State Bridge Corporation Ltd. bcusikkimupsbc@gmail.com
3 Ongoing Construction & Upgradation of existing road to 2-lane with paved shoulder from New Rolep Bridge at km 37.600 to Chochenpheri at km 52.00 in the section of Rongli to Chochenpheri of NH 717B (Pkg-II C) 14.40 478.79 16-03-2021 25-05-2021 58 51 23-05-2024 31-03-2026 Nalanda Engicon Pvt. Ltd.- Ujjain Engicon Pvt. Ltd. (JV) Pkg2c@nalandaengicon.com
4 Ongoing Construction of 2-lane road with paved shoulder (Greenfield alignment) of existing stretch between Legship - Gyalshing from km75.00 to km 90.210 under SARDP-NE Phase “A” on EPC Mode (Pkg- VI) 15.21 439.56 14-09-2020 10-11-2020 52 48 10-05-2022 31-03-2026 JRA Infrastructure Ltd. (JRAIPL) jra.ahmedabad@gmail.com
5 Ongoing Rehabilitation & Upgradation of existing road to 2-lane with paved shoulder including geometric improvement of section from start of Rabangla km33.600 to km58.840 under SARDP-NE Phase “A” (Pkg- IV) 25.24 292.80 31-08-2020 31-10-2020 61 58 01-05-2022 31-03-2026 Shivam Condev Pvt. Ltd. shivamsikkimpkgivnh510@gmail.com
6 Ongoing Construction/Upgradation of Existing road to 2 lane with paved shoulder including Geometric Improvement from Ranipool to Pakyong from km 2.000 to km 16.167 (Balance Work) under SARDP-NE 'A'” 14.17 380.94 02-11-2022 05-01-2023 75 72 06-07-2024 28-02-2026 Bhavya Construction bhavya.silchar@gmail.com

bhavya.sikkim@gmail.com
7 Ongoing Construction & Upgradation of existing road to 2-lane with paved shoulder from km27.200 (End of Rongli bypass) to km37.600(New Rolep Bridge) of Rhenok-Menla spur (NH-717B) on EPC Mode under SARDP-NE Phase-A in Sikkim (Pkg-II B) 10.40 244.91 31-08-2020 15-10-2020 83 80 15-04-2023 31-12-2025 J.K. Associates - A.K. Builders (JV) akjksiteoffice@gmail.com
8 Ongoing Construction of 2-lane with paved shoulder of new green field alignment from Helipad at Menla at km 82.00 to Menla at Km 94.030 of Rhenok-Menla Spur under SARDP-NE Phase 'A' on NH-717B (Pkg-III B) 12.03 379.30 28-12-2020 25-02-2021 75 73 24-02-2024 31-12-2025 A. G. Construction agconstruction.rhenok@gmail.com
9 Ongoing Realignment of NH717A from Design CH: 0.00 (Km 77.800 of NH-10) to Design CH:2.00 (Km 3.100 of NH-717A) with 2-lane paved shoulder including Major Bridge (viaduct) of 680 m on Ranipool to Pakyong road
(Surrendered & CoS work)
2.00 04-02-2021 10-04-2021 82 75 10-04-2023 30-10-2025 Suryodaya Infra Projects Pvt Ltd (SIPL) sipl.ranipool@gmail.com
10 Completed Construction and up-gradation of existing road to 2 - lane with paved shoulder including geometric improvement of NH-510 from km 16.000 to km 32.500 (Tarku - Rabongla) on EPC basic under SARDP-NE Phase ‘A’ in the state of Sikkim (Pkg- II) 16.50 290.05 31-03-2017 01-11-2017 100 100 31-10-2020 S&P lnfrastructure Developers Pvt. Ltd. snp.sikkim510@gmail.com
info@spinfra.in
11 Completed Construction of Rangpo-Viaduct of 826 m Viaduct Bridge at Rangpo between km 51.100 to 53.900 along with approaches with total project length of 1.123 Km on Sevoke – Gangtok road (NH-10) in the State of West Bengal and Sikkim under SARDP-NE Phase-A on EPC mode (Atal Setu) 1.12 133.49 16-12-2016 20-02-2017 100 100 20-02-2020 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL)
12 Completed Construction of 2-lane specification road with paved shoulder including Tunnel (300m) at Rabangla on NH-510 (Singtam-Tarku-Rabangla-Legship-Gyalshing) Pkg-III (Design Ch.: 32.500 km to 33.600 km) under SARDP-NE (Pkg- III) 1.10 79.21 22-09-2020 15-10-2020 100 98 15-10-2022 Nagyan Construction Pvt. Ltd. (NCPL) ncplsikkim@gmail.com
13 Completed Construction of 2-lane Chisopani Traffic Tunnel of length 250 m including approaches from Km 67+080 to Km 67+500 on NH-10 in East District of Sikkim on EPC basis. 0.42 35.69 05-03-2019 09-09-2019 100 100 08-09-2021 Nagyan Construction Pvt. Ltd. (NCPL)
14 Completed Constuction/Upgradation of existing road to 2 lane with paved shoulder from Km. 0.000 to Km. 26.706 in Rhenok-Rorathang-Pakyong as Alternate Highway to Gangtok on NH-717A on EPC Mode under SARDP-NE Phase-A in Sikkim 26.70 530.67 31-03-2017 01-11-2017 100 100 31-10-2020 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) draplanning.sikkim@gmail.com
15 Completed Construction of 2-lane with paved shoulder including geometric improvement from Km 0.000 to Km 16.000 of stretch Singtam- Tarku of NH 510 on EPC basis under SARDP-NE Phase ‘A’ in the state of Sikkim (Pkg- I) 16.00 375.80 26-02-2019 05-10-2019 97 95 05-04-2022 Vinod Kumar Jain (VKJ)-N Siva Prakash Reddy (NSPR) Constr. (I) Pvt. Ltd. (JV) vkjnsprjv@gmail.com
16 Completed Construction of 48m Bridge over Chuba Khola at Km 75+300 to Km 75+800 on NH-10 on EPC Mode in Sikkim 0.48 8.93 21-05-2019 16-09-2019 100 100 15-09-2021 Mohan Bajaj mohanbajajconstt@gmail.com