Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion/ Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Improvement/Widening of National Highway No. 217 (Dainadubi-Darugiri section) to Two lane with paved shoulder in Meghalaya from design Km 0+000 to Km 40+840 (Design Length=40.840Km) (existing Km 8+600 to Km 53+000 of Old NH-62) under BMP (Lot-1) Pkg-1B (Meghalaya portion) 40.84 705.83 31-03-2023 20-03-2025 5 20-03-2027 20-03-2027 Allone Infra Pvt. Ltd. -GaneshKartikey Construction Pvt. Ltd. (JV) singhconst2002@gmail.com
2 Ongoing Improvement/Widening to 2-L with Paved Shoulder/ 4-Laning of NH-40 section from Km 151+330 to Km 163+400 (design Km 63.530 to Km 71.520) including (Dawki Bridge of length 368 m) between Shillong-Dawki under JICA ODA Loan assistance (Phase-II) (Pkg-5) -Balance work 7.99 284.21 08-03-2024 17-05-2024 24 20 13-11-2026 13-11-2026 ASC Infratech Pvt. Ltd. sanjay@ascinfratech.com
3 Ongoing Construction of 2-Lane with paved shoulders of Shillong Western Bypass starting from NH-06 near Ladumsaw (existing Km 60.900 of old NH40) to NH106 (old NH 44E) (Package-III), from km 24+700 to km 38+256 under SARDP-NE PHASE A in the state of Meghalaya on EPC Mode (Greenfield alignment) 13.56 562.48 24-03-2023 02-09-2024 25 19 01-09-2026 02-09-2026 BRN Infrastructures Pvt. Ltd. brninfrastructure@gmail.com
4 Ongoing Construction of 2-Lane with paved shoulder of Shillong Western Bypass starting from NH-06 near Ladumsaw (Existing km 60.900 of old NH-40) to NH106 (old NH-44E), km 0+000 to km 12+800 (Package-I) under SARDP-NE ‘PHASE A’ in the State of Meghalaya on EPC Mode (Greenfield alignment) 12.80 620.30 24-03-2023 02-09-2024 33 24 01-09-2026 02-09-2026 Anusha Projects Pvt. Ltd.- BKD Infrastructures Pvt. Ltd. (JV) anushaprojects@gmail.com
5 Ongoing Construction of 2 lane with paved shoulder of Shillong Western Bypass starting from NH-06 near Ladumsaw (existing km 60.900 of old NH-40) to NH-106 (old NH-44E), (Package-II) km 12+800 to km 24+700 under SARDP-NE ‘Phase A’ in the State of Meghalaya on EPC Mode 11.99 686.03 24-03-2023 02-09-2024 24 21 01-09-2026 02-09-2026 Narendra Sharma - T.K. Engineering Consortium Pvt. Ltd. (TKECPL) (JV) nscdholpur@gmail.com
6 Ongoing Improvement/Widening to 2-Lane with Paved Shoulder between Shillong-Dawki road up to Bangladesh Border from (design Km 10.670 to Km 37.550) under JICA ODA Loan assistance (Phase-II) -Balance Work-(Pkg-2)
(with Toll Plaza at Ch. Km 22.850)
26.55 525.67 16-10-2023 09-02-2024 34 30 07-08-2026 07-08-2026 YFC Projects Pvt. Ltd. - ACE Construction (JV) info@linkcon.in
7 Ongoing Improvement/Widening to 2-Lane with Paved Shoulder from (design Km 45.760 to Km 63.530) between Shillong-Dawki under JICA ODA Loan assistance (Phase-II) -Balance work (Pkg-4) 17.77 445.51 22-01-2024 19-04-2024 31 30 19-04-2026 18-04-2026 ACE Construction - LEPL (JV) info@linkcon.in
8 Ongoing Rehabilitation and up gradation of Nongstoin-Rambrai-Kyrshai road up to Meghalaya-Assam border from Km 0.335 to km 34.039 to 2-Lane under NH(O) - NE in the State of Meghalaya (Package-1) 33.70 359.86 27-01-2022 27-05-2022 89 83 25-05-2024 31-12-2025 SPICA Projects & Infrastructures Pvt. Ltd. nongstoin.spica@gmail.com
9 Ongoing Improvement/Widening to 2-L with Paved Shoulder/4-L from Km 81+740 to Km 93+490 (design Km 0+000 to Km 10+670) of NH-40 (New NH-106 & 206) section & 4-L from (design Km 0.00 to Km 0.930) of NH-44 section between Shillong-Dawki under JICA ODA Loan assistance (Phase-II) -Balance Work-(Pkg-1) 11.60 351.12 24-07-2023 23-10-2023 63 59 22-10-2025 22-10-2025 New India Contractors & Developers Pvt. Ltd. - BCC Buildtech Pvt. Ltd. (JV) bcc.shillong03@gmail.com, office@nicdpl.com, bcc.shillong2024@gmail.com
10 Ongoing Widening to 2- lane with Geometric improvement of Tura-Dalu Road from Km 85.000 to Km 95.000 & Km 101.000 to km 145.000 to 2-lanes with paved shoulder of Tura- Dalu section under JICA ODA Loan assistance (Phase-I) 51.54 610.09 28-03-2018 15-09-2018 88 85 14-09-2021 15-06-2025 Manaranjan Brahma
nh51.turadalu.siteoffice@gmail.com
11 Awarded, not Appointed lmprovement/Construction to 2-lane with paved shoulders/4-laning of NH-40 (New NH-206) between Shillong to Dawki road upto Bangladesh Border including Dawki Bridge in the State of Meghalaya for execution on EPC Mode under NH (O)-NE from Existing Chainage Km 123.800 to Km 131.820 (design Km 0+000 to 7+760) (Package-III) Pynursla Bypass 7.76 564.07 22-05-2025 Dhar Construction Company-Royal Infraconstru Limited (JV) dccshg2@gmail.com
12 Completed 2 Lane with earthern shoulder from of Ranikor – Baghmara –Maheshkola Road Section from Ranikhor to Nongjri existing Km 0+000 to 31+700 (Design Length – 33.250 Km) EPC Mode in the state of Maghalaya under SARDP-NE Phase-A (Pkg-1) 30.20 306.28 09-03-2019 30-09-2019 100 99 29-03-2022 Dhar Construction Company - Chanchal Paul (JV) hvs_construction@rediffmail.com
13 Completed lmprovement/ widening to 2-laning with earthen shoulder of Panda (Design Ch. 112.300 km) to Baghmara (Design Ch. 129.385 km ) on SH-4 section of Ranikor- Maheshkhola- Baghmara Project in the state of Meghalaya under NH(O)-NE [R-M-B Package-6] 17.09 144.99 27-01-2022 30-09-2022 100 99 31-03-2024 Nidhi Creative Infrastructure Pvt. Ltd. nidhi.cipl@yahoo.in
nidhicreativebagmara@gmail.com
14 Completed Improvement/widening to 2-lane with Earthen shoulder of Ranikor-Maheshkhola- Baghmara road section from Kanai to Rongara, existing Ch. From Km 85.970 to Km 102.345 (Design Ch. From Km 81.100 to Km 96.000) Design length-14.763 km on EPC (Pkg-4) 14.76 146.92 30-09-2020 24-10-2020 100 99 25-04-2022 Narendra Sharma nscdholpur@gmail.com
nscbaghmara@gmail.com
15 Awarded, not Appointed Improvement and Widening of National Highway No. 127B (Darugiri - Songsak - Williamnagar Junction Section) to two lane with paved shoulder from design Km 0+000 to Km 36+635 (Design length= 36.635 Km) (existing Km 112+000 to Km 151+060 of NH-1278) under Bharatmala Pariyojana (Lot-1) Pkg-1B (Meghalaya portion) 36.64 801.07 31-03-2023 Shivalaya Construction co. Pvt. Ltd. (SCCPL) tenders@sccgroup.co.in
16 Completed lmprovement/widening to 2-laning with earthen shoulder of Nongjri (Design Ch. 30.00km) to Maheshkola (Design Ch. 55.525km )[R-M-B Package 2] on SH-4 section of Ranikor- Maheshkhola- Baghmara Project in the state of Meghalaya under NH (O)-NE (Pkg-2) 25.53 261.40 07-03-2022 19-12-2022 100 94 19-06-2024 Dhar Construction Company dccshg2@gmail.com
17 Completed Improvement/widening to 2-lane with Earthen shoulder of Ranikor-Maheshkhola- Baghmara road section from Rongara to Panda, existing Ch. From Km 102.345 to Km 119.810 (design Ch. From Km 96.00 to Km 112.300) design length-16.30 km on EPC (Pkg-5) 16.30 146.88 30-09-2020 24-10-2020 100 100 24-04-2022 Narendra Sharma aks.nh102a@gmail.com
akshivhare@rediffmail.com
akshivhare2015@gmail.com
18 Completed lmprovement/ widening to 2-laning with earthen shoulder from Maheshkola to kanai existing chainage from Ch. 59.270 to Ch. 85.970 (Design Ch. 55.525 to Ch. 79.680) on SH-4 Ranikor-Baghmara Project (Package-3) 24.16 260.21 27-03-2021 28-06-2021 100 99 28-12-2022 DMR Builders Pvt. Ltd. dmrmeghalayasite@gmail.com