Sorry, you need to enable JavaScript to visit this website.

Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion/ Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Construction of Intermediate Lane with Hard Shoulder of Hunli to Hayuliang (Package-I) from Design Km 0.000 to Km 53.000 (Design Length 53.000 km, Greenfield) Section of Frontier Highway (NH-913) in the State of Arunachal Pradesh on EPC Mode 53.00 1262.43 13-12-2024 01-03-2025 3 2 29-02-2028 29-02-2028 Bhartia Infra Projects Ltd-Shivam Transcon (JV) shivambhartiajv@gmail.com
2 Ongoing Construction of 2-Laning with hard shoulders of Demwe-Brahmakund section of NH-13 from Ch.0.00 km to 18.464 km on EPC under SARDP-NE (NH(O)-NE) -Balance Work 18.46 353.90 31-03-2025 18-12-2027 Spica Projects and lnfrastructures Pvt. Ltd spicaprojectspvtltd@gmail.com
3 Ongoing Construction of lntermediate Lane Road with hard shoulder from design chainage Km 0.000 to Km 53.040 (Existing Length:68.500 Km & Total Design length 53.04 km) of Tato to Monigong section of NH-913 (Frontier Highway) on Nafra (Bomdila) to Vijaynagar along China border in state of Arunachal pradesh on EPC mode 53.04 625.61 15-03-2024 15-05-2025 14-11-2027 14-11-2027 ABCI -Brand Eagles (JV) abcibe.jv@gmail.com
4 Ongoing Construction of Intermediate Lane of Pango to Jorging Road from 0+000 to Design Km Design Km 40+000 (Design Length: 40.00 Km, Pkg-l, Greenfield Alignment) in the State of Arunachal Pradesh on EPC mode (Pkg-1) 40.00 898.19 10-09-2024 14-01-2025 4 2 16-07-2027 16-07-2027 TTC Infra India ttcii.pango@gmail.com
5 Ongoing Construction of Intermediate Lane Road with hard shoulder from design Km 0.000 to Km 17.387 (Total length 17.387 km) of Hunli to Ithun Bridge section on NH-913 (Frontier Highway) in State of Arunachal Pradesh” on EPC mode under NH(O)-NE 17.39 275.50 15-03-2024 30-01-2025 9 5 30-01-2027 30-01-2027 J Infratech Limited (JIL) infojcipl@gmail.com
6 Ongoing Construction of 2-lane road from km. 0.00 (Existing km. 16.00 of Roing -Hunli Road) to Km. 74.00 (Ithun Bridge near existing km. 21.50 of Anini Road)-Green Field alignment 74.86 1718.59 24-03-2017 05-03-2018 74 72 04-03-2022 31-03-2026 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) - Iron Triangle (ITL) (JV) roymonpm1962@gmail.com
7 Ongoing 2-Laning with hard shoulders of Hayuliang– Hawai bypass Road on EPC basis from design Km. 51.825 to Km. 63.131 (Existing Km 45.050 of Hayuliang – Hawai road to Hawai Town) Pkg - IV under SARDP-NE -Balance work 11.30 216.76 31-03-2021 03-05-2021 93 92 02-05-2023 19-02-2026 Poddar Infratech Pvt. Ltd. - GRRB Associates (JV) poddargrrb@gmail.com
8 Ongoing Construction of 2-Laning with hard shoulder road of Ram- Mandir to Arrowa section of NH-113 from Design Km 0.000 to Km 2.910 (Existing Km 65.080 to Km 67.990) of total length 2.755 km excluding Tidding Bridge (155 m) on EPC mode 2.76 46.90 15-03-2024 28-06-2024 66 58 28-12-2025 28-12-2025 GRRB Associates grrb.tezu.hayuliang@gmail.com
9 Ongoing Construction of 1 Major bridges at Existing Ch. 23+650 (Design Ch. 23+550) of bridge span 160 m along the Existing Hunli-Anini Road (Pkg.1) from Km 21.500 to Km 37.500 on EPC mode
(CoS work at Km 23+650 & de-scoping of 1 MJR Bridge at Ch. 28+200)
0.16 60.00 28-09-2021 17-12-2021 70 70 19-06-2023 31-10-2025 Poddar Infratech Pvt. Ltd. varun@poddarinfra.com
10 Ongoing Construction of Balance work of 2-Lane with PS of Joram-Koloriang Road (NH-713) on EPC basis from Design Km 44.989 to Km 61.547 (Existing Km 50.050 to Km 70.000) in the state of Arunachal Pradesh under SARDP-NE (Pkg-3) 16.56 228.71 10-08-2020 01-10-2020 100 97 02-04-2022 31-07-2025 Valecha Engg. Ltd. contracts@valecha.in
11 Ongoing Construction of Balance Work of 2-Lane with Paved Shoulders of Joram-Koloriang Road (NH-713) on EPC basis from existing km 138.000 to km158.000 [Design km. 122.353 to km. 138.389] (design length – 16.036 km) in the state of Arunachal Pradesh under SARDP-NE (Pkg-8) 16.04 244.10 07-03-2022 07-05-2022 97 95 06-11-2023 31-07-2025 Puna Hinda Jainco Enterprises <jainco.kota@gmail.com> arunachaljainco@gmail.com
12 Ongoing Construction of Balance work of 2-Lane with PS of Joram – Koloriang Road from existing Km122.600 to km138.00 [Design Km108.724 to Km123.714] in Arunachal Pradesh on EPC Mode under SARDP-NE (Pkg-7) 14.99 184.88 07-08-2020 01-10-2020 97 96 02-04-2022 15-07-2025 Jainco Enterprises Pvt. Ltd. Jainco Enterprises <jainco.kota@gmail.com> arunachaljainco@gmail.com
13 Completed Construction of 2-lane road from design km. 21.50 (Near Ithun Bridge) to Km. 37.500 (existing Km 21.450 to Km 40.160) of Hunli-Anini road in the State of Arunachal Pradesh on EPC basis under SARDP-NE (Pkg.-1) 16.00 378.80 06-05-2016 21-12-2016 100 100 20-12-2019 Madhucon Projects Limited gm.bd@madhucon.com
14 Completed Construction of 2-lane of Hunli-Anini road from Existing km. 120.000 to Km. 130.300 on EPC basis under SARDP-NE - (Pkg.-6) 10.30 145.17 16-03-2018 15-06-2018 100 100 14-06-2021 TTC Infra India ttc.hapkg6@gmail.com
15 Completed Construction of 2-Lane with Paved shoulder of Joram – Koloriang Road (NH-713) from design Km. 32+050 to Km. 44+000 [Existing Km 35.150 to Km 50.050] in Arunachal Pradesh on EPC Mode under SARDP-NE (Pkg-2) 11.95 176.22 24-03-2017 22-04-2019 100 100 20-04-2022 T K Engineering Consortium Pvt. Ltd.(TKECPL) -Brand Eagles
(TKECPL - BE)
debajitdz501@gmail.com
16 Completed 2-Laning from Changlang/Tirap District Boundary to Changlang of NH-52B (New NH-215) from design km 0.00 to km 18.266 (length 18.266 km) in Arunachal Pradesh under Arunachal Pradesh package of SARDP-NE on EPC mode 18.27 172.75 31-03-2015 01-06-2015 100 100 31-05-2018 T K Engineering Consortium Pvt. Ltd.(TKECPL) tkeconltd@gmail.com
debajitdz501@gmail.com
17 Completed 2-Laning with hard shoulders of Khupa-Hayuliang-Hawai Road NH-113 on EPC basis from design Km. 0.000 (Khupa) to Km. 17.000 [Existing Km 95.800 of (Khupa – Hayuliang Road) to Km 8.970 (Hayuliang – Hawai Road)] Pkg - I under SARDP-NE 17.00 252.05 23-03-2017 10-11-2017 100 100 09-11-2020 Sushee Infra & Mining Limited susheehayuliang@gmail.com
puttakishore333@gmail.com
18 Completed 2-Laning with paved shoulder of NH-52 (New NH-13) from km 583.450 to km 605.600 (Existing chainage from km 583.450 to km 595.000) from Pasighat to Bomjur Road including Re-alignment from km 591.900 to km 602.600 in Arunachal Pradesh under Arunachal Pradesh package of SARDP-NE on EPC Mode 22.15 244.82 02-03-2016 24-02-2017 100 100 23-02-2020 Bhartia Infrastructures Projects Ltd. (BIPL) -ABL (JV ) Bipl.tinsukia@gmail.com
19 Awarded, not Appointed Construction of Intermediate Lane with Hard Shoulder of Hunli to Hayuliang (Package-III) from design Km 60.000 to Km 121.500 (Design Length 61.500 km, Greenfield) Section of Frontier Highway (NH-913) in the State of Arunachal Pradesh on EPC Mode 61.50 1418.67 30-10-2024 Bhartia Infrastructures Projects Ltd. (BIPL) biplpkg003@gmail.com
20 Completed Rehabilitation/ Restoration (One Time Improvement) of Hunli -Anini Road on NH-313 from km 0.00 to km 21.500 in the State of Arunachal Pradesh on EPC basis 21.50 23.56 22-02-2019 10-10-2019 100 100 09-10-2020 Nani Mamung Enterprises (NME-N.M. Enterprises) n.menterprises.n751@gmail.com
21 Completed Construction of 2-lane of Hunli-Anini road from Design Km 92.500 to Km 106.200 (Existing Km 97.670 to Km 111.600) on EPC basis under SARDP-NE - (Pkg.-4) 13.70 188.78 14-12-2016 19-01-2017 100 100 18-01-2020 Sushee Infra & Mining Limited ttc.hapkg6@gmail.com
22 Completed Construction of 2-lane with hard shoulder of Akajan-Likabali-Bame road from existing km 71.00 to km 99.00 (Design Km 65.810 to Km 91.928) in the state of Arunachal Pradesh under SARDP-NE (Pkg-3) 26.12 323.49 31-03-2017 21-03-2018 100 100 19-03-2021 SCIW-Shivam (JV) sciwshivamjv.nhidcl@gmail.com
23 Completed 2 laning from Mahadevpur to Buri Dihing Bridge point section (NH-52B) (New NH-215) of the stretch from 0.00 km. to 25.135 km in Arunachal Pradesh under Arunachal Pradesh package of SARDP-NE on EPC basis 25.14 136.60 31-03-2015 30-05-2015 100 100 30-05-2018 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) - Puna Hinda (JV) punahinda@gmail.com
24 Completed Construction of Balance work of 2-Lane with P S of Joram – Koloriang (NH-713) on EPC basis from existing km 88.700 to 104.850 [Design km. 78.724 to Km 93.724] in the state of Arunachal Pradesh under SARDP-NE (Pkg-5) 15.00 229.70 14-08-2020 01-10-2020 100 100 02-04-2022 Bhimji Velji Sorathia Construction Pvt. Ltd. kuvraji@yahoo.com
kbh@bvscpl.in
gm.jkroad@bvscpl.in
25 Completed 2-Laning from Pasighat to Pangin section of NH-229 (New NH-13) from km 41.3 to 58.420 (Existing Km 982.85 to Km 998.85 of Existing 16Km) (Section-III) under SARDP-NE in Arunachal Pradesh on EPC Mode 17.12 247.44 27-03-2015 27-05-2015 100 100 25-05-2018 T K Engineering Consortium Pvt. Ltd.(TKECPL) tkeconltd@gmail.com
debajitdz501@gmail.com
26 Awarded, not Appointed lmprovement and Widening to 2 lane with paved Shoulder of NH-15 (old NH-52) from Existing Km 770.600 (Design Km 24.819) to Existing km 805.750 (Design Km 59.885) (Kamlang T-Junction to Chowkham, Existing Length: 35.150 Km, Design Length-35.066 Km) in the state of Arunachal Pradesh on EPC mode (Pkg-2) 35.07 316.73 31-03-2025 Jayshree lnternational - BK Construction (JV) jayshreegroupttd@gmait. Com
27 Completed Construction of 2-lane existing Hunli-Anini road from Design km. 37.500 to Km. 53.500 (Existing km 40.160 to 56.320) on EPC basis under SARDP-NE - (Pkg.-2) 16.00 259.52 06-05-2016 07-10-2016 100 100 06-10-2019 Madhucon Projects Limited gm.bd@madhucon.com
28 Completed 2-Laning of existing Akajan-Likabali- Bame Road on EPC basis from design Km.12+000 to Km. 33+000 (existing Km.12+000 to Km.36+000) in the state of Arunachal Pradesh under SARDP-NE (Pkg-1) 21.00 210.50 02-11-2015 20-01-2016 100 100 18-01-2019 Jugal Kishore Mahanta Infra works (JKM)-Keti Constructions Limited (KCL) (JV) jkmlikabali@gmail.com
29 Completed 2-Lanning from Changlang/Tirap District Boundary to Khonsa of NH 52B (New NH 215) (Length 42.844 km) i in Arunachal Pradesh under Arunachal Pradesh package of SARDP-NE Phase-II on EPC mode 42.84 438.32 01-03-2016 15-06-2016 100 100 14-06-2019 MGCPL-HGIEPL (JV) delhi@mgcpl.com
30 Completed 2-Laning with hard shoulders of Hayuliang – Hawai Road on EPC basis from design Km. 17.000 (Khupa) to Km. 34.000 [Existing Km 16.950 to Km 34.310 (Hayuliang – Hawai Road)] Pkg - II under SARDP-NE 17.00 252.79 23-03-2017 10-11-2017 100 100 08-11-2020 Sushee Infra & Mining Limited susheehayuliang@gmail.com
puttakishore333@gmail.com
31 Completed Construction of 2-lane of Hunli-Anini road from Design km. 106.200 to Km. 120.00 on EPC basis under SARDP-NE - (Pkg.-5) 13.80 200.44 14-12-2016 19-01-2017 100 100 19-01-2020 Sushee Infra & Mining Limited puttakishore333@gmail.com
32 Completed Construction of 2-Lane with Paved shoulder of Joram – Koloriang Road (NH-713) from design Km. 20+000 to Km. 32+050 (Existing Km 20.000 to Km 35.150) in Arunachal Pradesh on EPC Mode under SARDP-NE (Pkg-1) 12.05 175.65 24-03-2017 22-04-2019 100 100 20-04-2022 T K Engineering Consortium Pvt. Ltd.(TKECPL) -Brand Eagles
(TKECPL - BE)
debajitdz501@gmail.com
33 Completed 2-Laning from Bordumsa-Namchik (Buri Dihing-Jairampur) road of NH-52B (New NH-215) from Km 0.15 km (starting Chainage near Buridihing Bridge) to km 22.380 in Arunachal Pradesh under Arunachal Pradesh package of SARDP-NE on EPC Mode 22.23 189.91 23-07-2015 23-10-2015 100 100 22-10-2018 Bhartia Infrastructures Projects Ltd. (BIPL)-Bharat Vanijya Eastern Pvt. Ltd.(BVEPL) (JV) biplbvepljv@rediffmail.com
34 Completed Construction of Balance work of 2-Lane with P S of Joram – Koloriang Road (NH-713) on EPC basis from existing km 104.850 to km 122.600 [Design km. 93.724 to km. 108.724] (Design length – 15 km) in the state of Arunachal Pradesh under SARDP-NE (Pkg-6) 14.60 199.03 17-08-2020 01-10-2020 100 100 02-04-2022 Jainco Enterprises Pvt. Ltd. arunachaljainco@gmail.com
jainco.kota@gmail.com
35 Completed Construction of 2-Laning with hard shoulders of Arrowa-Khupa-Hayuliang section of NH-113 from Ch.68.550 to Ch.91.633 on EPC mode under SARDP-NE (NH(O)-NE) 23.08 301.06 31-08-2020 25-10-2020 100 94 27-04-2022 M. P. (Mahabir Prasad) Agarwala Pvt. Ltd. mp.arrowa.khupa@gmail.com
36 Completed Construction of 2-Laning of Pasighat-Mariyang-Yingkiong road (New NH-513) from Singer River to Sijon River from 19.880km to 43.257km in Arunachal Pradesh under Arunachal Pradesh package of SARDP-NE on EPC basis 23.38 238.46 09-11-2015 15-01-2016 100 100 19-01-2019 ABL-BIPL (JV) Bipl.tinsukia@gmail.com
37 Completed Construction of 2-lane Hunli-Anini road from Design km 53.500 to km 92.500 (Existing Km 56.320 to Km 97.650) on EPC basis under SARDP-NE - (Pkg.-3) 39.00 516.70 12-09-2016 16-12-2016 100 98 15-12-2019 Progressive Construction Limited (PCL) -Eagle Infra India Limited (JV) pcl.etalin@gmail.com
38 Completed Construction of Balance work of 2-Laning of existing Akajan-Likabali- Bame Road on EPC basis from design Km 33.00 to Km 65.810 (Existing km 36.00 to km 71.00) in the state of Arunachal Pradesh under SARDP-NE (Pkg-2) 32.81 263.40 30-06-2021 01-09-2021 100 99 03-03-2023 MVV Satyanaryana mvvs.alb2@gmail.com
39 Completed Construction of Balance work of 2-Lane with P S of Joram – Koloriang Road (NH-713) on EPC basis from Design Km 61.547 to Km 78.724 (Existing Km 70.000 to Km 88.700) in the state of Arunachal Pradesh under SARDP-NE (Pkg-4) 17.18 294.04 11-08-2020 01-10-2020 100 99 02-04-2022 Bhimji Velji Sorathia Construction Pvt. Ltd. gm.jkroad@bvscpl.in
40 Completed 2-Laning from Kanubari to Longding Section of NH-52B (New NH215) From km.0.000 to km. 47.213 (DPR Length 47.213 km & Design length 45.600) in Arunachal Pradesh under Arunachal Pradesh package of SARDP-NE on EPC mode 45.60 522.87 31-03-2015 02-06-2015 100 100 26-11-2018 Monte Carlo Ltd. kanubari.ap@mclindia.com
41 Completed 2-Laning from Pasighat to Pangin section of NH-229 (New NH-13) from km 0 to Km 28 (Existing Km 1013.85 to Km 1041.85) of 28 Km (Section-I) under SARDP-NE in Arunachal Pradesh on EPC Mode 26.58 299.66 31-03-2015 27-05-2015 100 100 25-05-2018 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) punahinda@gmail.com
42 Completed 2-Laning with hard shoulders of Hayuliang – Hawai Road on EPC basis from Design Km. 34.000 to Km. 51.825 [Existing Km 26.625 to Km 45.050 (Hayuliang – Hawai Road)] Pkg - III under SARDP-NE 17.83 263.31 23-03-2017 10-11-2017 100 100 09-11-2020 Sushee Infra & Mining Limited susheehayuliang@gmail.com
43 Awarded, not Appointed lmprovement and Widening to 2-lane with Paved Shoulder of NH-13 & 15 (Old NH-52) from Existing Km 745.60 (Design Km 0.000) to Existing km 770.600 (Design Km 24.819) (Brahmakund T-junction to Kamlang T-Junction, Existing Length: 25.00 Km, Design Length: 24.819 Km) in the state of Arunachal Pradesh on EPC mode (Pkg-1) 24.82 441.41 31-03-2025 TTC lnfra lndia-M/s Lopon Enterprises (JV) info@ttcinfraindia.com