Sr. No. | Project Status | Name of Project | Length (Km) | TPC (Rs. in Cr) | Date of Award | Appointed Date | Cumulative Physical progress ( %) as Per PMIS | Cumulative Financial progress (%) as Per PMIS | Original Schedule Completion Date | Likely Date of completion/ Actual Date of Completion | Name of the Contractor | Official Mail IDs of Contractor |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ongoing | Construction of Major Bridge over Middle Strait Creek between Km. 106.590 to Km 108.553 of NH-223 (New NH-04) connecting South Andaman and Baratang Islands in UT of A&N islands on EPC mode | 1.96 | 371.88 | 16-03-2024 | 07-05-2024 | 5 | 25-02-2026 | 25-02-2026 | RKEC Projects- YFC (JV) | msbridge@rkecprojects.com | |
2 | Ongoing | Rehabilitation and up-gradation and completion of balance work of section from Km 155.00 to Km 181.00 (End of Jarwa to Rangat) of NH -4 (Total length 26 Km) to Intermediate Lane/2-lane with hard shoulders in the UT of A&N Islands on EPC basis - (Package-III)-B Balance work | 26.00 | 333.12 | 16-03-2024 | 07-05-2024 | 34 | 16 | 05-10-2025 | 05-11-2025 | RKEC Projects Ltd. | roadpkg3@rkecprojects.com |
3 | Ongoing | Rehabilitation of section from Km 298.00 to Km 330.662 (Karala to Kalipur) of NH-04 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-VIII) | 32.66 | 109.33 | 13-04-2021 | 01-07-2021 | 88 | 78 | 01-07-2023 | 30-09-2025 | Kaba Infratech Pvt. Ltd. | shivam.agrawal@kabagroup.com |
4 | Ongoing | Rehabilitation and up-gradation of section to Intermediate/2-Lane with hard shoulder from Km 107.760 to Km 129.445 (After Middle strait to Humphrey), Km 130.600 to Km 138.00 (After Humphrey to Kadamtala) of NH-04 in the Union Territory of Andaman & Nicobar Islands on EPC (Package-IIIA)-Balance work | 29.41 | 376.48 | 25-01-2024 | 14-03-2024 | 39 | 29 | 13-09-2025 | 12-09-2025 | SMC Infrastructures | andaman3a.smcipl@gmail.com |
5 | Ongoing | Rehabilitation and up-gradation to 2-Lane with hard shoulder of section from Km 242.0 to 298.0 of NH-223 (New NH-4) in UT of A&N islands on EPC mode (Package-II) | 55.47 | 409.85 | 31-03-2017 | 05-12-2017 | 95 | 94 | 04-12-2019 | 31-07-2025 | Vasishta Constructions Pvt. Ltd. - Mantena Infra LLP NH (JV) | aditya.k@vasishta.in |
6 | Ongoing | Rehabilitation and up-gradation to 2-Lane with hard shoulder of section from Km 206.00 to Km 242.00(Design Ch. 239.425) (Nimbutala to Austin Creek) of NH-223 (New NH-4) in UT of A&N islands on EPC mode (Package-IV) | 33.41 | 234.27 | 27-03-2018 | 04-09-2018 | 83 | 79 | 03-09-2020 | 31-07-2025 | Vasishta Construction Pvt.Ltd | aditya.k@vasishta.in |
7 | Completed | Rehabilitation of Km 0.00 to Km 12.00 section in Andaman Trunk Road of NH-4 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-V) | 12.00 | 32.54 | 14-02-2019 | 02-04-2019 | 100 | 100 | 31-03-2020 | Mohan Mutha Exports Pvt Ltd | 1) dkmutha@mmexport.com 2) pkmutha@mmexports.com |
|
8 | Completed | Rehabilitation and Up-gradation of Jarwa area of NH-223 (New NH-4) from Km 59.40 to Km 107.00 (Jarwa-I) and Km 138.30 to Km 155.00 (Jarwa-II) in UT of A&N islands on Item Rate basis | 64.30 | 59.56 | 05-03-2018 | 09-04-2018 | 100 | 100 | 09-04-2019 | J Infratech Limited (JIL) | 1) hoplanningjcipl@gmail.com 2)janduconstco@yahoo.com |
|
9 | Completed | Rehabilitation of Km 181.00 to Km 206.00 section in Andaman Trunk Road of NH-4 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-VII) | 25.00 | 71.93 | 28-11-2018 | 01-01-2019 | 100 | 100 | 31-12-2019 | Garg & Sons Estate Promoters Pvt Ltd | 1) racgrag@yahoo.com 2) racgarg260@gmail.com |
|
10 | Completed | Rehabilitation and up-gradation to 2-Lane with hard shoulder of section from Beodnabad- Ferrargunj section of NH-223 (New NH-04) from Km 12.000 to 45.000 (excluding Km 21.0 to 28.0) in UT of A&N islands on EPC mode (Package-I) | 25.93 | 176.76 | 01-03-2017 | 01-11-2017 | 100 | 100 | 31-10-2018 | Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) | prabaharan@sreeinfratech.com | |
11 | Completed | Rehabilitation of section from Km 45.00 to Km 59.20 of NH-4 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-VI) | 14.10 | 59.08 | 14-02-2019 | 02-04-2019 | 100 | 100 | 31-03-2020 | Mohan Mutha Exports Pvt Ltd | 1) dkmutha@mmexport.com 2) pkmutha@mmexports.com |
|
12 | Completed | Construction of Major Bridge (Bridge Length- 1020m) over Humphrey Strait Creek between Km.129.420 to Km. 130.600 of NH-223 (New NH-04) connecting Middle & North Andaman Island in the UT of Andaman and Nicobar Islands on EPC Basis "Azad Hind Fauz Setu" | 1.45 | 271.07 | 15-02-2017 | 26-04-2017 | 100 | 100 | 25-04-2020 | MBZ -RDS (JV) | mayank.goyal@rdsproject.com |