Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion/ Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Construction of Major Bridge over Middle Strait Creek between Km. 106.590 to Km 108.553 of NH-223 (New NH-04) connecting South Andaman and Baratang Islands in UT of A&N islands on EPC mode 1.96 371.88 16-03-2024 07-05-2024 5 25-02-2026 25-02-2026 RKEC Projects- YFC (JV) msbridge@rkecprojects.com
2 Ongoing Rehabilitation and up-gradation and completion of balance work of section from Km 155.00 to Km 181.00 (End of Jarwa to Rangat) of NH -4 (Total length 26 Km) to Intermediate Lane/2-lane with hard shoulders in the UT of A&N Islands on EPC basis - (Package-III)-B Balance work 26.00 333.12 16-03-2024 07-05-2024 34 16 05-10-2025 05-11-2025 RKEC Projects Ltd. roadpkg3@rkecprojects.com
3 Ongoing Rehabilitation of section from Km 298.00 to Km 330.662 (Karala to Kalipur) of NH-04 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-VIII) 32.66 109.33 13-04-2021 01-07-2021 88 78 01-07-2023 30-09-2025 Kaba Infratech Pvt. Ltd. shivam.agrawal@kabagroup.com
4 Ongoing Rehabilitation and up-gradation of section to Intermediate/2-Lane with hard shoulder from Km 107.760 to Km 129.445 (After Middle strait to Humphrey), Km 130.600 to Km 138.00 (After Humphrey to Kadamtala) of NH-04 in the Union Territory of Andaman & Nicobar Islands on EPC (Package-IIIA)-Balance work 29.41 376.48 25-01-2024 14-03-2024 39 29 13-09-2025 12-09-2025 SMC Infrastructures andaman3a.smcipl@gmail.com
5 Ongoing Rehabilitation and up-gradation to 2-Lane with hard shoulder of section from Km 242.0 to 298.0 of NH-223 (New NH-4) in UT of A&N islands on EPC mode (Package-II) 55.47 409.85 31-03-2017 05-12-2017 95 94 04-12-2019 31-07-2025 Vasishta Constructions Pvt. Ltd. - Mantena Infra LLP NH (JV) aditya.k@vasishta.in
6 Ongoing Rehabilitation and up-gradation to 2-Lane with hard shoulder of section from Km 206.00 to Km 242.00(Design Ch. 239.425) (Nimbutala to Austin Creek) of NH-223 (New NH-4) in UT of A&N islands on EPC mode (Package-IV) 33.41 234.27 27-03-2018 04-09-2018 83 79 03-09-2020 31-07-2025 Vasishta Construction Pvt.Ltd aditya.k@vasishta.in
7 Completed Rehabilitation of Km 0.00 to Km 12.00 section in Andaman Trunk Road of NH-4 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-V) 12.00 32.54 14-02-2019 02-04-2019 100 100 31-03-2020 Mohan Mutha Exports Pvt Ltd 1) dkmutha@mmexport.com
2) pkmutha@mmexports.com
8 Completed Rehabilitation and Up-gradation of Jarwa area of NH-223 (New NH-4) from Km 59.40 to Km 107.00 (Jarwa-I) and Km 138.30 to Km 155.00 (Jarwa-II) in UT of A&N islands on Item Rate basis 64.30 59.56 05-03-2018 09-04-2018 100 100 09-04-2019 J Infratech Limited (JIL) 1) hoplanningjcipl@gmail.com
2)janduconstco@yahoo.com
9 Completed Rehabilitation of Km 181.00 to Km 206.00 section in Andaman Trunk Road of NH-4 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-VII) 25.00 71.93 28-11-2018 01-01-2019 100 100 31-12-2019 Garg & Sons Estate Promoters Pvt Ltd 1) racgrag@yahoo.com
2) racgarg260@gmail.com
10 Completed Rehabilitation and up-gradation to 2-Lane with hard shoulder of section from Beodnabad- Ferrargunj section of NH-223 (New NH-04) from Km 12.000 to 45.000 (excluding Km 21.0 to 28.0) in UT of A&N islands on EPC mode (Package-I) 25.93 176.76 01-03-2017 01-11-2017 100 100 31-10-2018 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) prabaharan@sreeinfratech.com
11 Completed Rehabilitation of section from Km 45.00 to Km 59.20 of NH-4 to Intermediate lane with hard shoulder in UT of A&N islands on EPC mode under NH(O) (Package-VI) 14.10 59.08 14-02-2019 02-04-2019 100 100 31-03-2020 Mohan Mutha Exports Pvt Ltd 1) dkmutha@mmexport.com
2) pkmutha@mmexports.com
12 Completed Construction of Major Bridge (Bridge Length- 1020m) over Humphrey Strait Creek between Km.129.420 to Km. 130.600 of NH-223 (New NH-04) connecting Middle & North Andaman Island in the UT of Andaman and Nicobar Islands on EPC Basis "Azad Hind Fauz Setu" 1.45 271.07 15-02-2017 26-04-2017 100 100 25-04-2020 MBZ -RDS (JV) mayank.goyal@rdsproject.com