Sorry, you need to enable JavaScript to visit this website.

Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion/ Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Construction of
(I) Connecting road from Z-Morh Tunnel to Zojila Tunnel (Road Length= 18.475km) in F.Y.- 2020-21 and

(II) 14.150 Km long 2-L Bi- directional single tube Zoji-la Tunnel accross Zojila Pass on Sonamarg - Kargil section from Km 82 to Km 118 of NH-01 under PMDP
30.89 6808.69 25-08-2020 01-10-2020 64 59 30-09-2026 29-02-2028 Megha Engineering & Infrastructures Ltd (MEIL) meilplanning.zojila@meghaeng.com
2 Ongoing Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to Km20.300 of 7.450Km length on Goha-Khellani section and a link road to Goha village of 2.016 km on NH-244 in UT of Jammu and Kashmir on EPC Mode (Pkg-1) 9.46 225.37 31-07-2020 01-10-2020 90 86 01-04-2022 31-10-2026 OASIS - VIPL (JV) info@oasisprojects.com

pkg1a.goha@gmail.com
3 Ongoing Construction of Kishtwar bypass with 2 lane with paved shoulder from Design Km. 80.675 (Dulhasti) to km 95.550 (Bandarkoot ) of 14.88 km & a link road to Kishtwar town from 0+000 to 1.871 of length=1.871 Km on Khellani - Kishtwar - Chattroo section in UT of Jammu and Kashmir on EPC Mode (Pkg-4) 16.75 859.67 07-07-2021 24-08-2021 45 45 23-08-2023 30-06-2026 APS Hydro Pvt. Ltd. - Unique Construction (APS - UC) (JV) apshydro@gmail.com

rohit.malik@apshydro.com
4 Ongoing Construction & Upgradation to 2-lane with paved shoulder from Design Ch. Km 51+700 (at Premnagar km 66+315) to Km 66+535 New Thatri (at Start of Km 83rd, Tunnel Km 82+665) of 14.835 Km design length on Chenani-Sudhmahadev-Goha Khellani-Kishtwar-Vailoo Donipawa-Ashajipora section of NH-244 in the UT of J&K on EPC Mode under NH(O)-Gen (Pkg - 2) 14.84 512.43 19-07-2021 26-08-2021 52 47 24-02-2023 30-06-2026 Mathiyan Construction Pvt. Ltd. - Unique Construction (JV) mathiyan_mzn@rediffmail.com

pm.jk@mathiyan.com
5 Ongoing Construction of Bi-directional Tunnel at "Km 83" of Length 495 m including approach road of 664 m and a Major Bridge of 110 m from Design Ch. 66.535 to Ch. 67.805 (Existing Km 82.675 to Km 82.925) (Khellani-Kishtwar) on NH-244 in UT of J&K on EPC Mode under NH(O) 1.27 91.29 07-02-2020 08-06-2020 50 48 07-06-2022 31-03-2026 Beigh Construction Co. Pvt. Ltd. beigh.bcc@gmail.com

md.bccpl@gmail.com,
6 Ongoing Upgradadtion of existing 2 lane to 4-L with Paved Shoulder configuration from Km 26.350 (Design Chainage 26+615) (Khati Chowk) to Km 30.097 (Design Chainage 30+359) (Hanuman Chowk) including bridge on Chenab river of Jammu - Akhnoor Section of NH 144A (Pkg-3B) 3.74 198.28 14-12-2022 14-03-2023 82 71 13-03-2025 31-12-2025 V. K. Gupta & Associates 1. amitkumar@vkga.in
2. contact@vkga.in
3. vkg.brconst@gmail.com
7 Ongoing Construction of a 4-Lane elevated flyover with paved shoulder configuration along with service road from 4th Tawi bridge (D.Ch. 0.000) near Bhagwati chowk to Canal Head (D.Ch. 1.350) on Jammu-Akhnoor road section of NH-144A (Pkg-1) 1.35 245.34 24-09-2022 10-01-2023 41 37 09-01-2025 31-10-2025 Maan Builders maanbuildersjammu@gmail.com

maanbuilderspkl@gmail.com
8 Ongoing Up-gradation to 4-lane with Paved Shoulder of Jammu-Akhnoor road section of NH-144A from Ganesh Vihar (Km 6.000) to Khati Chowk (Km 26.350) in UT of Jammu and Kashmir on EPC basis (Pkg-3A)
1 No. TOLL of 8- Lane @ Ch. 20+440
20.35 435.82 02-03-2019 12-07-2019 82 81 11-07-2021 31-08-2025 Tarmat Ltd. tarmatakhnoor@gmail.com
9 Ongoing Construction/upgradation to 2-lane with paved shoulder from Design Km 95.55 (Bandarkoot) to Km. 111.06 (Chattroo) of 15.52 Km length on Chenani-sudhmahadev-Goha-Khellani-Kishtwar-vailoo-Donipawa-Ashajipoora section on NH-244 in UT of Jammu and Kashmir on EPC Mode (Pkg-5) 15.52 497.09 13-07-2021 24-08-2021 90 85 19-02-2023 31-08-2025 Shree Girrajjee Infra Heights Pvt. Itd. - Narendra Builders (SGIHPL-NB) (JV) sginbpkg5@gmail.com
10 Ongoing Up-gradation to 2-lane with Paved Shoulder from Km 20.300 to Km 29.030 of 8.730 Km length on Goha-Khellani section on NH-244 in UT of Jammu and Kashmir on EPC Mode (Package II) 8.73 210.79 31-07-2020 01-10-2020 94 90 01-04-2022 31-07-2025 E5 Infrastructure Pvt. Ltd. package2gohakhellani@gmail.com

construction@e5infra.com
11 Ongoing Widening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geometric improvement from Km 0.000 to Km 16.990 on Chenani – Sudhmahadev section of NH-244 in UT of Jammu and Kashmir to be executed on EPC basis 16.99 264.21 27-03-2018 22-11-2018 91 93 21-11-2020 30-06-2025 ECI Engineering & Constr. Co. Ltd. - SRM Projects (JV) srmcontractors@gmail.com
srmcplc@gmail.com
12 Completed Up-gradation to 2-lane with Paved Shoulder form Km 29+030 to Km 31+449 of 2.419 Km length of Uni-Directional (1.574 Km) Khellani Tunnel including its approach road on NH-244 in UT of Jammu and Kashmir on EPC Mode under NH(O)-Gen (Package III) 2.42 749.61 08-02-2021 25-03-2021 100 100 24-03-2023 APCO Infratech Pvt. Ltd ddbabu@apcoinfra.com

dc.ktp@apcoinfra.com
13 Completed construction of New 2-Lane bypass from Design Km 176+532 (Existing km 263+070; (Donipawa) to Design Km 185+002 (Near Khudwani on NH-44 at Existing km 238+500) Alstop via Ashajipora of 8.470 Km length i.e., to connecting NH-244 & NH-44 (Pkg-7) 8.47 260.40 30-03-2021 15-06-2021 100 98 16-12-2022 E5 Infrastructure Pvt. Ltd. syedaesan821@gmail.com
14 Completed Restoration of Road by way of clearance of landslide, surface boulders side drain, culverts including construction of R/wall/Scuppers and laying of WBM-II, WBM-III, & Pre- Mixed Surfacing/Mixed seal Surfacing (PC) on Batote-Kishtwar-Chatroo- Sinthan top road NH-244 Km from Km 170.000 to Km 184.000 on Item Rate basis 14.00 8.01 01-03-2018 07-03-2018 100 100 31-08-2019 Khandey Infra Pvt Ltd
directorkipl@gmail.com
15 Completed Construction & Upgradation to 2 lane with paved shoulder from Design Km. 31.449 (Khellani) (Ex. Km 44.946) to Km 51.700 (Prem Nagar) (Ex. Km 68+617) of 20.251 Km length on Khellani - Kishtwar - Chattroo section of NH-244 in the UT of J&K on EPC Mode under NH(O)-Gen (PKG- 1) 20.25 486.45 03-02-2021 29-03-2021 97 97 28-09-2022 R&C Infra Engineers Pvt. Ltd.- SKS Infra Projects Pvt. Ltd. (JV) randcinfraengineers@gmail.com
randcdodaoffice@gmail.com
16 Completed Strengthening & Upgradation of existing carriageway to intermediate lane from km 0.000 to km 42.820 of Length 42.820kms on Baramulla-Gulmarg section of NH-701A in the UT of Jammu & Kashmir on EPC mode 42.82 131.60 31-08-2020 08-10-2020 100 100 05-04-2022 United Jehlum Road Roof Builders - Jehlum Construction Co (JV) danish.mir3@gmail.com
17 Completed Up-gradation to 4-lane with Paved Shoulder of Jammu-Akhnoor road section of NH-144A from Canal head (Km 0.800) to Ganesh Vihar (Km 6.000) in UT of Jammu and Kashmir on EPC basis (Pkg-2) 5.20 458.06 15-03-2018 07-08-2018 100 100 04-02-2021 Satpal (S. P.) Singla construction Pvt. Ltd.[SPSCPL] salwanguleria@spsingla.com,
spsakhnoor@spsingla.com
18 Completed Construction & Upgradation to 2-lane with paved shoulder from Design Km 67.805 (at the end of Km 83rd Tunnel near Dhrabshalla) (Ex. Km 83+905) to Km 80.675 (start of Kishtwar Bypass - Dulhasti) (Ex. Km 97+0751) of 12.870 Km length on chenani-Sudhmahadev-Goha Khellani-Kishtwar-vailoo-Donipawa-Ashajipora section of NH-244 in the UT of J&K on EPC Mode under NH(O)-Gen (Pkg-3) 9.12 398.51 30-03-2021 01-07-2021 98 94 31-12-2022 R & B Infra Project Pvt. Ltd legal@rathoregroup.co
19 Completed Construction & Upgradation to 2/ 4-Lane with paved shoulder from Design Km 148+589 (Existing km 235+070) (Vailoo )to Design Km 176+532 (Existing km 263+070) Donipawa of 27.943 km length on Khellani-Khanabal section (PKG- 6) 27.94 285.28 03-02-2021 31-03-2021 100 100 30-09-2022 New India Contractors & Developers Pvt. Ltd. - Khanday Infrastructure Ltd. (JV) directorkipl@gmail.com
20 Completed Restoration of road by way of clearance of landslide, surface boulders side drain, culverts including construction of R/wall and B/walls and laying of WBM-I, WBM-II, WBM-III & Bituminous Carpeting on Sinthanpass- Anantnag –Khanabal road (Km 184.00 to Km 265.000) on Item Rate basis 23.20 16.49 16-02-2018 22-03-2018 100 100 31-08-2019 Khandey Infra Pvt Ltd
21 Completed Construction Operation and Maintenance of 2L bi-directional single tube Z-Morh Tunnel (Sonamarg Tunnel)of 6.412 km long with parallel 6.426 km long escape tunnel and 0.6 km long Ventilation Tunnel with approaches of length 5.568 Km from approximately km 69.000 to km 81.300 on new alignment between Kullan and Sonmarg in the UT of Jammu and Kashmir under Srinagar-Leh section on NH-1 (Srinagar- Sonamarg- Gumri road) on DBFOT (semi-Annuity basis) 11.98 2716.90 19-12-2019 24-06-2020 100 100 20-12-2023 APCO Infratech Pvt. Ltd dksaini@apcoinfra.com