Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Slope protection and landslide mitigation at 4 vulnerable locations (km 1.950 to Km 2.100, km 11.100 to 11.450, km 22.435 to km 22.485 and km 22.610 to km 22.680) within Sevoke-Rangpo section of NH-10 (old NH-31A) in Darjeeling & Kalimpong district in the State of West Bengal on EPC mode
0.62 152.27 10-01-2025 26-06-2025 31 23 26-06-2027 26-06-2027 Geo-spar Infra Pvt. Ltd.- SVS Mookambika Construction Pvt. Ltd.(SVSMC) (JV) info@spargrp.com
2 Ongoing Slope Stabilization Scheme at location of landslide at km 52.240 km & Km 42.800 of NH-110 at Tindharia, West Bengal & Permanent Restoration of damaged Road under NH Division-IX in the district of Darjeeling, West Bengal during the year 2022-23
0.13 24.52 06-09-2024 77 75 09-03-2026 30-11-2026 Pavai Infra Geotech, Coimbatore, Tamilnadu. info@pavaigeotech.com
3 Ongoing Slope Protection and Landslide Mitigation at 2 Vulnerable locations viz. Km 23.200 to 23.960, Km 26.530 to Km 26.580 within Sevoke-Rangpo section of NH-10 (old NH-31A) in Kalimpong district in the State of West Bengal on EPC mode 0.81 68.49 12-07-2024 06-09-2024 5 0 08-03-2026 08-11-2026 Nagyan Construction Pvt. Ltd. (NCPL)
4 Ongoing Improvement of Spots including reconstruction and widening of Culverts in between Ch. km 40.000 to km 65.000 of NH-55 (New NH-110) under NH Division – IX (I) in the District of Darjeeling, West Bengal in the FY 2024-25
2.84 32.35 23-04-2025 23-04-2025 66 57 21-04-2026 31-08-2026 Daljyor Unemployed Engineer’s Co-operative Society Ltd. daljyor2008@gmail.com
5 Ongoing Improvement of Spots (Including widening of culvert, drops & guide) from km 4.390 to km 4.585, km 5.328 to km 5.430, km 8.520 to km 9.075 (At 02 nos. of locations), km 9.335 to km 9.520 and km 12.060 to 12.235 on NH-110 (Old NH-55) in between km 0.00 to km 20.00 of NH-110 under NH Division-IX in the District of Darjeeling, West Bengal [2023-24/RSEC-15]
1.21 15.02 17-03-2025 52 26 16-03-2026 31-08-2026 Sun Shine Overseas Pvt. Ltd. sopl.ebp@gmail.com
6 Completed Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenok-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (from Km 0.00 to Km 13.00 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal) PKG- IVA 15.24 402.94 01-03-2019 04-10-2019 99 75 03-04-2022 30-08-2026 N Siva Prakash Reddy (NSPR) Constr. (I) Pvt. Ltd. - Vinod Kumar Jain (VKJ) (JV) nsprvkj.bagrakot@gmail.com
7 Completed Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of sect. from Pedong bypass to Reshi Border km 79.700 to km 96.254 of NH-717A under SARDP-NE-A on EPC as part of Alternate connectivity to Gangtok (Lava More-Reshi Border ) Pkg-VB 16.55 395.59 24-07-2020 20-10-2020 97 91 17-04-2022 30-08-2026 TTC Infra India - Suryodaya Infra Projects Pvt Ltd (SIPL) (JV) ttc.prpkgvb@gmail.com
8 Ongoing Reconstruction and widening of 08 nos. narrow culvert at km 22.445, km 22.450, km 22.840, km 27.565, km 29.000 ( half portion), km 29.500, km 30.650, km 38.290 & spot improvement from km 22.397 to km 22.442, km 22.445 to km 22.450, km 22.453 to km 22.493, km 26.855 to km 26.935, km 27.125 to km 27.175, km 27.492 to km 27.562, km 27.565 to km 27.710, km 29.487 to km 29.502, km 29.506 to km 29.513, km 32.710 to km 32.750, km 32.885 to km 32.910, km 38.185 to km 38.285, km 38.290 to km 38.330 & Repair of old parapets, construction of new parapet, road signage such as Median Marker, Road Marking etc. in selected stretches from km 20.00 to km 40.00 of NH-110 ( Old NH-55) in the district of Darjeeling under Annual Plan 2022-23
0.66 13.49 25-01-2024 01-03-2024 94 92 28-02-2025 15-08-2026 DDSD Construction Co. ddsdcc12@gmail.com
9 Ongoing Improvement of Spots from 21.710 km to 21.838 km (including reconstruction & culvert widening), 21.921 km to 22.000 km (including drop & guides), 23.760 km to 23.800 km, 26.597 km to 26.705 km (including drop & Guides), 28.270 km to 28.340 km, 35.878 km to 35.980 km, 36.025 km to 36.135 km, 36.245 km to 36.400 km (including reconstruction & culvert widening) on NH-110 (old NH-55) in between km 20.00 to km 40.00 of Nh-110 (old NH-55) under NH Division No.-IX in the dist. of Darjeeling
0.79 14.48 11-09-2024 97 94 11-09-2025 15-08-2026 Kundan Tamang kundantamangslg@rediffmall.com
10 Ongoing Construction & upgradation of existing road to 2-lane with paved shoulder including geometric improvement of Kafer- Lava More section from km 40.00 to km 61.100 of NH717-A on EPC under SARDP-NE A in state of West Bengal (Pkg-VA) 21.10 273.78 21-08-2020 05-10-2020 96 94 05-04-2023 30-07-2026 Rani Constructions Pvt. Ltd. - Sri Satya Sai Infrastructrue Pvt. Ltd. (JV) nh717a.5a@ranigroup.com
11 Ongoing Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenock-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (from Km 13.00 to Km 25.60 of Bagrakot -Kafer section of NH 717A on EPC Mode under Phase-A of SARDP-NE in the State of West Bengal) PKG- IVB 12.60 295.97 19-08-2020 05-10-2020 98 95 05-04-2023 30-07-2026 Rani Constructions Pvt. Ltd. - Sri Satya Sai Infrastructrue Pvt. Ltd. (JV) nh717a.4b@ranigroup.com
12 Completed Construction of alternative highway to Gangtok in Sikkim via Bagrakot -Chuikhim-Nimbong -Kafer-Bakhim-Algarah-Rhenock in the State of West Bengal and from Rhenock-Rorathang-Pakyong along with spur from Aritar-Rolep-Menla in the State of Sikkim (Package No. IVD from Km 26.10 to 40.00 of Bagrakot - Kafer section of NH 717A on EPC Mode under Phase A of SARDP-NE in the State of West Bengal) PKG- IVD 13.90 242.97 20-03-2020 11-06-2020 100 99 10-06-2022 02-01-2024 Ketan Construction Ltd.(KCL)-Bhutan Builders Pvt. Ltd.(BBPL) (JV) kclbbpl2020@gmail.com
13 Completed Construction of Rangpo-Viaduct of 826 m Viaduct Bridge at Rangpo between km 51.100 to 53.900 along with approaches with total project length of 1.123 Km on Sevoke – Gangtok road (NH-10) in the State of West Bengal and Sikkim under SARDP-NE Phase-A on EPC mode (Atal Setu) 1.12 133.49 16-12-2016 20-02-2017 93 81 20-02-2020 08-06-2022 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL)
14 Awarded, not Appointed Widening of Valley side at 3 locations viz. Km 20.900, Km 35.500 and Km 36.700 and culvert at 13 locations viz. Km 17.600, Km 17.800, Km 18.300, Km 20.200, Km 21.500, Km 21.650, Km 21.850, Km 32.800, Km 33.100, Km 38.300, Km 40.300, Km 43.700, Km 47.300 2.20 75.85 12-02-2026 0 0 Tvastar Infratech Pvt. Ltd.
15 Awarded, not Appointed Slope Protection and Landslide Mitigation at 3 Vulnerable Locations (from actual chainages 6.50 to Ch. 6.705, Ch. 7.17 to Ch. 7.25 and Ch. 22.800 to Ch. 22.950) within Sevoke -Rangpo section of NH-10 (old NH 31A) in the district of Kalimpong in west Bengal
0.00 57.21 03-02-2026 0 0 Bharat Constructions (India) Pvt. Ltd.
16 Completed Construction of Mechi bridge (of 675m) and Approaches of 2/4- Lane with paved shoulder on NH-327B across Indo-Nepal
border on Asian Highway (AH -02) by ADB fund under SASEC Tranche-2 on EPC mode
1.50 158.65 23-11-2017 01-02-2018 100 98 30-01-2021 05-09-2020 Dineshchandra R. Agarwal Infracon Pvt. Ltd. (DRAIPL) draiplmechi@gmail.com