Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Widening & Up-gradation to 2 lane with paved shoulder of NH-301 Kargil- Zanskar Road from Design Km .30.040 (Ex. Km. 30.000) to Design Km 57.000 (Ex. Km. 57.905) of 26.960 Km length (Pkg-II) 26.96 404.89 31-03-2021 01-07-2021 75 71 02-01-2023 31-03-2026 Topline Infra Projects Pvt. Ltd. topline.infra@gmail.com
2 Ongoing Widening & Up-gradation to 2 lane with Paved shoulder of NH-301 Kargil- Zanskar Road from Design km 57.000 (Ex. Km. 57.905) to Km 87.000 (Ex. Km. 88.2491) of 30.000 Km length (Pkg-lll) 30.00 381.11 31-03-2021 01-07-2021 83 76 02-01-2023 31-03-2026 Topline Infra Projects Pvt. Ltd. topline.infra@gmail.com
3 Ongoing Widening & Up-gradation to 2 lane with paved shoulder of NH-301 Kargil Zanskar Road from Design Km 196.250 (Ex. Km.
194.1901 to Design Km 230.020 (Ex Km. 231.692) of 33.770 Km length (PKG-Vlll)
33.77 398.37 31-03-2021 01-07-2021 91 86 02-01-2023 28-02-2026 Satish Aggarwal & Co. sarccompany@gmail.com
4 Ongoing Up-gradation to 2 lane with Paved shoulder of NH-301 Kargil- Zanskar road from km 87+00 to KM 98+524 in the UT of Ladakh(Formally State of J&K) on EPC Mode (PKG-IV) 11.52 214.21 05-08-2020 02-03-2021 90 83 01-03-2024 28-02-2026 United Jehlum Road Roof Builders united.kargil.nh301@gmail.com
5 Completed Up-Gradation to 2 lane with Paved shoulder of NH-301 Kargil- Zanskar Road from Km 148+320 to Km. 196+250 in the UT of Ladakh (Formerly State of J&K) on EPC mode (PKG-VII) 47.93 498.71 27-01-2021 14-06-2021 100 98 13-06-2024 01-12-2023 S&P lnfrastructure Developers Pvt. Ltd. - Skylark lnfra Engineering Pvt Ltd. (JV) planning.epc@skylarkworld.com
6 Completed Up-gradation to 2 lane with Paved shoulder of NH-301 Kargil- Zanskar road from Km 98+524 to Km. 117+180 in the UT of Ladakh (Formally State of J&K) on EPC Mode (PKG-V) 18.65 313.39 11-08-2020 10-12-2020 100 95 09-12-2023 26-06-2023 S&P lnfrastructure Developers Pvt. Ltd. - Skylark lnfra Engineering Pvt Ltd. (JV) planning.epc@skylarkworld.com
7 Completed Construction of 1x15 M Span Bridge at Km 125.493, 1x20 M Span Bridge at Km 125.852 and 1x10 M Span Bridge at Km 129.445 including its approaches on Kargil-Zanskar Road (NH-301) on EPC Mode 0.04 34.11 28-08-2020 01-06-2021 100 100 01-07-2024 30-06-2024 Hafiz Construction Pvt Ltd hafizconstco@gmail.com
8 Completed Up-Gradation to 2 lane with Paved shoulder of NH-301 Kargil- Zanskar Road from Km 117+180 to Km. 148+320 in the UT Ladakh (Formerly State of J&K) on EPC mode (PKG-VI) 31.14 400.09 27-01-2021 24-05-2021 100 96 23-05-2024 01-12-2023 S&P lnfrastructure Developers Pvt. Ltd. - Skylark lnfra Engineering Pvt Ltd. (JV) planning.epc@skylarkworld.com
9 Completed Construction of 1x45 m Bridges including its approaches on NH-301 at Km 130.230 , Kargil-Zanskar Road in the UT of Ladakh on EPC Mode 0.04 18.21 21-08-2020 01-07-2021 100 98 01-07-2024 30-06-2024 Hafiz Construction Pvt Ltd sgfjammu@gmail.com
10 Completed Construction of 1x25 M Span Bridge at Km. 165.296, Km. 172.965 and Km. 185.509 including its approaches on NH-301, Kargil-Zanskar Road on EPC Mode (Bridge-3) 0.07 28.48 28-08-2020 01-06-2021 100 100 01-07-2024 03-01-2024 SGF Infra Pvt Ltd hafizconstco@gmail.com