Sr. No. Project Status Name of Project Length (Km) TPC (Rs. in Cr) Date of Award Appointed Date Cumulative Physical progress ( %) as Per PMIS Cumulative Financial progress (%) as Per PMIS Original Schedule Completion Date Likely Date of completion Actual Date of Completion Name of the Contractor Official Mail IDs of Contractor
1 Ongoing Construction of 4-Lane Bridge including approaches over River Brahmaputra between Dhubri (on North Bank,Assam) and Phulbari (on south Bank,Meghalaya) on NH-127B under JICA ODA Loan assistance (Phase-III) 19.28 4997.04 24-11-2020 15-12-2020 67 64 12-09-2028 12-09-2028 Larsen & Toubro Ltd. Heavy Civil Infrastructure IC Larsen & Toubro Ltd.(L&T) dpbplnt@gmail.com
2 Ongoing lmprovement to 4-Lane with Paved Shoulder from existing km 260+000 (Design Ch.4+560 km) to existing km Ch.233+000 (D. Ch.24+560) of Silchar (near Nutan Dayapur village) - Budha Nagar Section (Length-20.00 Km) of NH-37 under Package: Silchar-Jiribam Pkg-1 in the state of Assam on HAM Mode 20.00 957.95 11-03-2024 15-01-2025 22 8 15-01-2028 15-01-2028 Silchar Jiribam Highways Private Limited headoffice@dccinfra.co.in
3 Ongoing Widening/lmprovement to 4-Lane with Paved Shoulder from existing road and Greenfield alignment form Design Ch. 62.800 (start of proposed Nilambazar/Cheragi Bypass) to Design Ch. 87.700 near Chandkhira Village of NH-8 on Silchar-Churaibari in the state of Assam on HAM Mode (Package-5) 24.90 1258.13 11-03-2024 26-04-2025 0 0 23-10-2027 23-10-2027 Bhartia Infra Projects Ltd ccb_silchar@yahoo.co.in
4 Ongoing Widening/lmprovement to 4-Laning and Greenfield alignment with Paved shoulder of Silchar-Badarpur – Churaibari section of NH-37 & NH-8 from Design chainage 38.600 (End point of proposed Badarpur Bypass) to Km. 62.800 (Start point of proposed Nilambazar/Cheragi Bypass) in the state of Assam on HAM Mode (Package-4) 24.20 1319.55 11-03-2024 18-08-2025 0 0 18-09-2027 18-09-2027 MKC Badarpur Churaibari Kamakhya Highways Pvt. Ltd. engineering@mkcinfrastructureltd.com
5 Ongoing Widening/lmprovement of Existing 2 lane to 4-Laning of Karimganj-Silchar section of NH-37 from Design Ch 0.000 near Silchar ISBT to Design Ch 15.970 near Kalinagar Pt I on NH-37 in Assam on HAM Mode (Pkg-1) 15.97 1181.55 11-03-2024 17-09-2025 0 0 17-09-2027 17-09-2027 Jandu Silchar Highway Pvt. Ltd. jandu.panchgram@jinfratech.com
6 Ongoing Widening/lmprovement to 4-Lane with Paved Shoulder from Ch.5.580 Km to Ch.25.633 Km (Design Ch.0.000 Km to Ch.17.737km) (Km 901.100 to Km 921.145 of old NH-31) of Bilasipara- Guwahati road (NH-17) (Section: Near Chirakuta to near Mowatari, before Chapar Bypass) in the state ol Assam on HAM mode (Package-1)
17.74 1081.15 11-03-2024 05-02-2025 6 0 04-08-2027 04-08-2027 Bilasipara Guwahati Pvt. Ltd. finance@bhartiainfra.com
7 Ongoing Widening/Improvement to 4-Lane with paved Shoulder from Ch. 25.633 Km to Ch. 52.470 Km (Design Ch. 21.850 Km to Ch.48.670 Km) for Package-2 of Bilasipura- Guwahati road (NH-17) (Section: Near Mowatari, before Chapar Bypass to Tulungia (junction with NH-17)) in the state of Assam on HAM mode under NH(O)-NE (Package-2)
26.82 1338.61 11-03-2024 05-12-2024 4 0 03-06-2027 03-06-2027 Naresh Kumar Garg Infrastructure Ltd. (NKG)-Mowatari Guwahati Road Pvt. Ltd. nkg@nkginfra.com
8 Ongoing Widening/lmprovement to 4-Lane with Paved shoulder for existing as well as Greenfield alignment of Badarpur – Churaibari section of NH-8 from Design chainage 87.700 (Chandkhira) to Km. 106.500 (Churaibari) section (Assam-Tripura border) in the state of Assam on HAM Mode (Package-6) 18.80 870.00 11-03-2024 07-03-2025 11 8 07-03-2027 07-03-2027 MKC Infra Ltd.. engineering@mkcinfrastructureltd.com
9 Ongoing Widening/lmprovement to 4-L of Karimgani - sutarkandi section of NH 37 from design Ch 0+020 (Start of proposed Karimganj Bypass from NH -8) to design Chainage Km 14+380 near Sutarkandi (Spur Connectivity to Indo/Bangladesh Border) on Silchar-Churaibari in the State of Assam on HAM Mode (Package-7) 14.36 791.79 11-03-2024 28-02-2025 5 0 28-02-2027 28-02-2027 MKC Infra Ltd.. engineering@mkcinfrastructureltd.com
10 Ongoing Construction of 4-Lane Panchgram Bypass from Design Chainage km 15+500 on NH-37 (Old NH-53) at Kalinagar Pt.-I Village to Design Chainage km 27+300 at crossing with NH-6 (Old NH-44) Near Siddeswar Pt.-I Village on Silchar - Churaibari stretch in the State of Assam on EPC Mode under Bharatmala Pariyojana in Economic Corridors (Silchar- Churaibari Package-2)
11.80 728.97 01-11-2023 10-08-2024 46 41 09-02-2027 09-02-2027 J Infratech Limited (JIL) isbt.silchar@jinfratech.com
11 Ongoing Widening/Improvement to 4-Lane with paved shoulder from Km 99+930 to Km 143+680 (Design Chainage 96+000 to 139+750) of (Paikan to Dhupdhara Sahar) of Bilasipura-Guwahati Road on NH-17 in the state of Assam on EPC mode under Bharatmala Pariyojana in Economic Corridors (Project Length – 43.750km) under NH(O)-NE (Package-8)
43.75 1457.59 14-03-2023 27-12-2023 57 50 26-12-2026 25-12-2026 YFC Projects Pvt. Ltd. - TTC Infra India (JV) ttcii.bg.pkg8@gmail.com
12 Ongoing Construction of New 2-Lane Bridge with its approaches from km 0+000 to Km 4+385 across River Brahmaputra on NH-17 at Jogighopa in Assam on EPC mode
4.38 746.76 10-08-2021 12-11-2021 73 71 10-11-2024 18-12-2026 Satpal (S. P.) Singla construction Pvt. Ltd.[SPSCPL] spsjogighopa@spsingla.com
13 Ongoing Widening/Improvement to 2-Lane Lane with Paved Shoulder from km 16+900 (Bogapani) to km 27+150 (Golai Goan) on existing Dibrugarh to Ledo section with proposed Digboi Bypass (Green Field and Brownfield) (2-Lane+PS) of NH-315 (OLD NH-38) in Tinsukia District under NH(O)- NE (Pkg-4) 10.25 356.65 28-02-2023 08-12-2023 23 19 06-12-2025 06-12-2026 RK Infracorp Pvt. Ltd. rkinfradigboiproject2023@gmail.com
14 Ongoing Widening/Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Srirampur (near Bhairiguri Village) to Kachukhana Harichara Paglagaunj (Package-I) of Srirampur - Dhubri Section of NH-127B from existing Km 0.000 to Km 28.050 (Design Km 0.000 to Km 27.650), (Design Length=27.650 Km) under JICA ODA Loan assistance (Phase-V) -Balance work
27.65 613.89 06-09-2024 25-11-2024 44 37 25-11-2026 25-11-2026 R&C Infra Engineers Pvt. Ltd-J Infratech Limited (JIL) (JV) rc.jandupkg1@jinfratech.com
15 Ongoing 4-Laning of Dhanehari Lailapur / Vairengte section from Existing Chainage km 12+920 to km 43+000 of NH 306 (Design Chainage km 20+000 to km 49+360) on Silchar - Vairengte Sairang road in the State of Assam under Bharatmala Pariyojna on EPC mode. (Project Length 29.360 km) under NH(O)-NE (Package-2)
29.36 1716.21 31-03-2023 14-02-2024 65 61 14-08-2026 14-08-2026 J Infratech Limited (JIL) jandu.silchar@jinfratech.com
16 Ongoing Construction of 4-Lane Badarpur Bypass from Design Chainage km 27+300 at crossing with NH-6 (Old NH-44) Near Siddeswar Pt.-I Village to Design Chainage km 38+600 on NH-37 (Old NH-44) at Kandigram Chaita Village on Silchar - Churaibari stretch in the State of Assam on EPC Mode under Bharatmala Pariyojana in Economic Corridors (Silchar- Churaibari Pkg-3)
11.10 574.26 16-03-2023 09-02-2024 55 49 09-08-2026 10-08-2026 S S Builders badarpurkmr@gmail.com
17 Ongoing 4-Laning of Silchar - Dhanehari section from Existing Chainage km 263+800 of NH 37 to km 12+920 of NH 306 (Design Chainage km 0+000 to km 20+000) on Silchar - Vairengte - Sairang road in the State of Assam under Bharatmala Pariyojna on EPC mode (Package-1)
20.00 1256.90 21-03-2023 22-01-2024 48 44 23-07-2026 22-07-2026 YFC Projects Pvt. Ltd. - TTC Infra India (JV) ttcii.sd.pkg1@gmail.com
18 Ongoing Widening/ Improvement to 4-Lane with Paved Shoulder from
Ch. 177+372km to Ch.203+783km (Design Ch.173+434km to Ch.200+750km) of Bilasipura- Guwahati road (NH 17) (Section:
Milmila R.F (before Chayagaon Market) to Approach of Airport Junction (VIP Chowk) in the State of Assam on EPC mode
under Bharatmala Pariyojana in Economic Corridors (Project Length - 27.316km) for (Package-10)
27.31 1264.90 31-03-2023 18-12-2023 39 29 18-06-2026 18-06-2026 ANIL Das - SAILAJA Commercial Construction Pvt. Ltd. (JV) anilsailajaprojectspkg10@gmail.com
19 Ongoing Widening/Improvement to 4-Lane with Paved Shoulder from
Ch. 143+680km to Ch.177+372km (Design Ch.139+750km to Ch.173+434km) of Bilasipura- Guwahati road on NH-17 (Section: Dhupdhara Sahar to Milmila Reserve Forest (before Chayagaon Market)) in the state of Assam on EPC mode under Bharatmala Pariyojana in Economic Corridors (Project Length –33.684km) NH(O)-NE (Package-9)
33.68 1000.27 20-03-2023 11-12-2023 40 27 11-06-2026 11-06-2026 ANIL Das - SAILAJA Commercial Construction Pvt. Ltd. (JV) anilsailajaprojects@gmail.com
20 Ongoing Widening/Improvement to 4-Lane with Paved Shoulder from km 55+000 (Nagabang Gamsuk) to km 82+514 (Oyan) in the State of Assam and Arunachal Pradesh on EPC mode under Bharatmala Pariyojna of Length 27.514 Km (Package-3) 27.51 665.47 31-03-2023 16-09-2024 73 66 17-03-2027 31-03-2026 Kaluwala Construction Pvt. Ltd.-Nirmal Buildinfra Pvt. Ltd. (JV) kcpl.assam@kaluwalaconstruction.in
21 Ongoing Widening/Improvement to 4-Lane with Paved Shoulder from km 626+030 (Nalani hulla Gaon) to km 650+450 (Chotahapjan) on existing Tinsukhia -Makum Bypass of NH-15 (OLD NH-37) and Strengthening of existing NH-315 (OLD NH-38) from Km 0+000 (Chotahapjan) to Km 16+900 (Bogapani section) (2-Lane +PS) in Assam on EPCMode under NH(O)-NE (Pkg-3) 41.32 458.59 03-02-2023 19-05-2023 72 70 17-05-2025 31-03-2026 TTC Infra India ttcii.tm@gmail.com
22 Ongoing Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 136.500 near Hejaichak to km 156.489 near P. Leikul (Package-9) on EPC mode under NH(O)-NE (Package-9)
19.98 614.43 31-03-2023 29-08-2023 70 51 29-08-2025 31-03-2026 pc.nh137@kpc.co pc.nh137@kpc.co
23 Ongoing Wideinig & Upgradation to 2-lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 96.870 near Jiri River to km 116.550 near Hangrum (Package-7) on EPC mode (Package–7)
19.68 846.82 22-01-2024 04-03-2024 72 68 04-03-2026 04-03-2026 Rajinder Infrastructure Pvt.Ltd. official.riplassam@gmail.com
24 Ongoing Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 490.800 to Km 534.800, under SARDP- NE on EPC Mode in the state of Assam Pkg- IV: (Structures & Toll Plaza) 0.00 100.22 19-08-2024 18-10-2024 49 43 13-10-2025 28-02-2026 Bhardwaj Unibuild Pvt. Ltd. bupljd4@gmail.com
25 Ongoing Widening & Upgradation to 2-lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 116.480 near Hangrum to km 136.500 near Hejaichak (Package-8) on EPC mode under NH(O)-NE (Package 8)
20.02 904.04 31-03-2023 29-08-2023 69 60 29-08-2025 28-02-2026 Anusha Projects Pvt. Ltd.- BKD Infrastructures Pvt. Ltd. (JV) appl.tmr8@gmail.com
26 Ongoing Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 501.800 to Km 514.800 (13.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-II: Road Works) 13.00 542.87 06-08-2024 10-10-2024 53 49 05-10-2025 28-02-2026 Bharat Vanijya Eastern Pvt. Ltd.(BVEPL) contact@bvepl.com
27 Ongoing Widening/Improvement to 4-Lane with Paved Shoulder from KM 38+500 to Km 51+246 (Design Chainage 38+500 to 50+959) with proposed Daboka Bypass of Daboka-Parokhaowa of NH 29 on EPC under NH(O)-NE (Package-1)
12.46 516.88 24-02-2023 30-11-2023 91 90 29-11-2025 28-02-2026 Mehta Construction Co. mehtapkg1nh29@gmail.com
28 Ongoing Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 514.800 to Km 534.800 (20.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-III: Road Works) 20.00 619.70 06-08-2024 03-10-2024 60 57 28-09-2025 28-02-2026 Kaushal Sharma ksharma.tsk@gmail.com
29 Ongoing Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 156.489 near P. Leikul to km 176.410 near Borowapu on EPC mode under NH(O)-NE (Assam portion) (Package-10)

19.92 693.15 31-03-2023 29-08-2023 67 59 29-08-2025 28-02-2026 Anusha Projects Pvt. Ltd.- BKD Infrastructures Pvt. Ltd. (JV) anushaprojects@gmail.com
30 Ongoing Widening & Improvement to 2-lane with Paved shoulder configuration of Dudhnoi - Dainadubi section (NH-217) under Bharatmala Pariyojana from design km 0+000 to km 8+415 (existing km 0+000 to km 8+600 of Old NH-62) in the State of Assam on EPC mode under NH(O)-NE, (Assam portion) 8.41 88.56 31-03-2023 26-03-2024 77 72 25-09-2025 31-01-2026 Shyama Construction shyamaconstructionnh217@gmail.com
31 Ongoing Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old) from Km 453.000 to Km 490.800, under SARDP- NE , under EPC Mode in the state of Assam : Pkg-IV (Structures & Toll Plaza) 279.01 15-01-2024 14-02-2024 96 92 11-08-2024 31-01-2026 Sadguru Engineers & Allied Services Pvt. Ltd. seaspvtltdghy@gmail.com
32 Ongoing Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old) from Km 463.00 to Km 477.000 (14.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-II: Road Works) 14.00 438.44 15-01-2024 14-02-2024 96 92 11-08-2024 31-01-2026 Binni Construction binniconstruction73@gmail.com
33 Ongoing Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 490.800 to Km 501.800 (11.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-I: Road Works) 11.00 476.50 06-08-2024 03-10-2024 81 78 28-09-2025 31-01-2026 Regal Enterprises regaljdpkg1@gmail.com, regal.jitender@gmail.com
34 Ongoing 4-Laning from Rangagara to Kaliabor Tiniali from km 297.00 to km 315.315 of NH-37 on EPC basis under SARDP-NE in state of Assam
18.32 462.88 16-01-2017 23-10-2017 88 87 21-04-2020 17-01-2026 Simplex Infrastructures Ltd. c3172@simplexinfra.com
35 Ongoing Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old): Pkg-III: Road Works from Km 477.000 to Km 490+800 (13.800 Km), under SARDP- NE under EPC Mode in the state of Assam 13.80 358.72 15-01-2024 14-02-2024 99 99 11-08-2024 15-01-2026 M. P. (Mahabir Prasad) Agarwala Pvt. Ltd. mpagarwalapvtltd@gmail.com
36 Ongoing Construction of Balance Work of 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old) from Km 453+000 to Km 463+000 (10.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-I: Road Works) 10.00 478.30 15-01-2024 14-02-2024 97 93 11-08-2024 15-01-2026 Sadguru Engineers & Allied Services Pvt. Ltd. seaspvtltdghy@gmail.com
37 Ongoing Widening/lmprovement to 4-Lane with Paved Shoulder from Dillai at Km 146+230 to Lahorijan at Km 157+46O (Design
Chainage 145+712 to 156+502) of Dillai - Lahorijan (Package -7)
10.79 204.10 02-09-2022 20-01-2023 97 95 20-07-2024 15-01-2026 Shankar Agarwal nh29pkg7sa@gmail.com
38 Completed Widening/improvement to 4-Lane with paved shoulder from km. 606+300 to km 626+030 of NH-37 on existing Lahoal-Chabua Bypass i.e. Kandulibari Grant Gaon to Nalanihulla section in Assam on EPCMode under NH(O)-NE [Pkg-2] 19.73 170.95 05-04-2022 25-07-2022 100 99 24-07-2024 22-08-2024 Jugal Kishore Mahanta Infra works (JKM) jkmahanta@jkminfra.net, jkmho@jiminfra.net, jkmdbrproject@gmail.com
39 Completed 4-Laning of Balachera-Harangjao section of NH-54 (ext.) (New NH-27) from km 275.00 to km 244.00 in the state of Assam on EPC mode under East-West corridor project under NHDP-II 25.25 887.68 31-10-2017 26-12-2017 100 99 24-06-2020 15-04-2024 Sushee Infra & Mining Limited - JSC Purpetruboprovodstroy (JSC PTPS) (JV) planning.balachera@gmail.com
40 Completed Improvement and Strenghtening of Road Section from Chand Khera to Kurti Bridge on NH-208A on (Assam-Tripura Border) in the state of Assam on EPC Mode under NH(O) 17.95 66.94 04-10-2016 28-11-2016 100 98 24-01-2018 31-03-2018 Ganesh Ram Dokania
41 Completed 4-Laning of NH-37 (New NH-127) from Teliagaon to Rangagara (km 288.600 to km 297.000) in the state of Assam under SARDP-NE Phase-A on EPC mode–Package-2 8.40 170.28 20-03-2020 01-07-2020 100 98 23-12-2021 30-03-2023 Ganga Sagar Singh support@gss.org.in
42 Completed 4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass from Km 182.000 to Km 208.000 of NH-52 on EPC mode in state of Assam under SARDP-NE
26.00 735.17 13-10-2016 19-12-2016 100 92 19-06-2019 30-07-2025 T.K. Engineering Consortium Pvt. Ltd. (TKECPL) info@ganpatibharat.com
43 Completed Widening/lmprovement to 4-Lane of Daboka Dimapur Stretch from Km 95+400 to Km 113+830 (Design Chainage 96+400 Km to 113+830 Km) of Ganpath Gaur Gaon- Kwaram Taro Vitlage in the state of Assam under Bharatmala Pariyojana on EPC mode (Package-5) 17.43 288.85 31-03-2021 12-07-2021 100 99 12-01-2023 19-11-2024 B.K.Sons Infra Pvt. Ltd. info@bksonsinfra.com
44 Completed Widening / Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Kachukhana Harichara Paglagaunj to Dhubri - Phulbari Bridge approach (Package-II) of Srirampur - Dhubri Section of NH-127B from existing Km 28.050 to Km 55.060 (Design Km 27.650 to Km 54.154), (Design Length=26.504 Km) under JICA ODA Loan assistance (Phase-V) [Srirampur - Dhubri Pkg-2]
26.50 909.02 04-08-2022 02-01-2023 100 98 01-01-2025 30-06-2025 J Infratech Limited (JIL) assam.pkg2@gmail.com, assam.pkg2@jinfratech.com
45 Completed Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel junction near Lapetketa ((Km. 561.700-Km. 580.875) under SARDP-NE, Phase 'A' in the State of Assam on EPC mode Pkg-II: Structures 0.00 55.96 26-07-2024 16-09-2024 100 98 14-03-2025 12-08-2025 Mehta Construction Co. mccmobostr@gmail.com
46 Completed 2-laning with paved shoulders from km 6.25 to 10.40 including RoB (Railway Over Bridge) at Srikona Railway Level Crossing at km 9.901 of Silchar- Badarpur section of NH-53 in state of Assam under SARDP-NE 4.15 76.78 23-03-2015 01-10-2015 100 98 11-12-2017 10-06-2022 Shree Gautam Construction Company Ltd. sgcclsilchar@gmail.com
47 Completed Widening/Improvement to 4-Lane with Paved Shoulder from km 0+800 (Kandulijan Gaon) to km 27+701 (Simen Chapori) of NH-515 in the State of Assam on EPC mode under Bharatmala Pariyojna (Dibrugarh-Oyan, Package-1) 26.90 609.16 31-03-2023 18-10-2023 100 99 17-04-2026 11-08-2025 Kaluwala Construction Pvt. Ltd.-Nirmal Buildinfra Pvt. Ltd. (JV) kcpl.assam@kaluwalaconstruction.in
48 Completed 4-Lane highway connecting km 17.300 of old NH-37A (New NH-715) and km 182 of NH-52 (New NH-15) between Dolabari and Jamuguri Section in Assam on EPC basis under SARDP-NE, Phase-A 16.86 592.01 05-11-2021 07-02-2022 100 95 08-08-2023 13-12-2023 BN Infra Project LLP mkcilrsmjv@gmail.com, jatin.s@rsminfra.in, jiabharali.dc@mkcinfrastructureltd.com
49 Completed Widening/Improvement to 4-Lane with Paved shoulder from km 66.00 to km 81.00 (Design Chainage 65.923 to 80.930) of Dokmoka - LoringThepi section- (Package-3) 15.01 266.26 10-08-2020 30-09-2020 100 97 24-03-2022 27-12-2022 Skylark Infra Engg. Pvt. Ltd. pm.dokmoka@skylarkworld.com
50 Completed, C.C. under issue INFRASTRUCTURE WORK: MMLP (Pkg.-III : External Rail Connectivity) 3.76 09-10-2020 01-12-2020 93 90 01-06-2022 20-09-2024 Sumcon Infraventures LLP gunjan@sumconinfraventures.com
51 Completed 4-Laning of Numaligarh to Jorhat section from Km. 402.500 to Km. 453.000 (Design Km 403.200 to Km 454.240) of NH-37 except construction of Dergaon bypass from Km 426.800 to Km 437.420 (Design Km 427.400 to 438.720) 39.72 1655.44 31-10-2014 23-05-2015 99 98 22-05-2018 15-03-2024 Hindustan Construction Company (HCC) njrp.pd@hccindia.com, njrp.qclab@hccindia.com, njrp@hccindia.com
52 Completed 4-Laning of NH-37 Section between Demow to End of Moran Bypass (From Km. 534.800 to Km. 561.700) including Emergency Landing Facility (ELF) under SARDP-NE, Phase 'A' in the State of Assam on EPC mode 26.90 385.57 14-10-2022 20-01-2023 100 98 20-07-2024 14-07-2025 Mohan Lal Jain msmljaindurgapur@yahoo.com
53 Completed Construction and up gradation to 4-Lane of existing two lane with paved shoulder from Hapachara to Tulungia road of NH-117 of existing Km 0.00 to km 14.050 and (Design Km 0.000 to km 14.660) under BMP on EPC mode
14.66 224.85 26-03-2020 26-06-2020 98 93 26-12-2022 30-06-2024 B.K.Sons Infra Pvt. Ltd. info@bksonsinfra.com
54 Completed One time improvement of Moran Town section of NH-37 from km 555.000 to km 558.500 in Assam on EPC Mode under NH(O) 3.50 14.52 31-05-2019 19-08-2019 100 82 17-08-2020 31-12-2020 BB Enterprises binudborgohain1972@gmail.com
55 Completed Widening/Improvement to 4-Lane with paved shoulder from Ch.75.330Km to Ch.88.00km (Design Ch.71.800 to 84.100 km) of Jogighopa Bridge Approach (Near Pancharatna)- Agia (near Nichinta) section of Bilasipura-Guwahati road (NH-17) on EPC under BMP (Package-6) 11.78 203.20 25-08-2020 26-10-2020 100 100 19-04-2022 06-07-2024 Mayasheel Construction msc.pkg6@gmail.com
56 Completed NFRASTRUCTURE WORK: MMLP (Package-I: Road and Utility Works) 4.25 693.97 05-06-2020 30-09-2020 100 96 01-04-2022 30-09-2024 RAM CHANDRA PAUL ram_chandrapaul@yahoo.in
57 Completed Up-gradation to 4-Laning from end of Biswanath Chariali by-pass (Km 208.000) to Gohpur (Km 265.500) of NH-52 (New NH-15) (Total length 57.50) in the state of Assam on EPC basis Under SARDP-NE
(with Toll Plaza at Ch. 219+200)
57.50 1451.16 18-10-2021 11-12-2021 100 98 14-06-2023 15-12-2023 Dhatarwal Construction Company Pvt. Ltd. babulsayan@gmail.com, babulnath40@gmail.com, dolabari.jamuguri@gmail.com
58 Completed Widening/Improvement to 4-Lane with Paved Shoulder from KM 113+300 to Km 146+230 (Design Chainage 113+830 to 145+712) of Kwaram Taro Village - Dillai Section (Package-6) 31.88 625.64 10-09-2021 14-07-2022 100 98 13-07-2024 31-03-2025 Ashoka Buildcon Ltd. ablnh29pkg6@ashokabuildcon.in
59 Completed Widening/improvement to 4-Lane with paved shoulder from km. 581+700 to km 606+300 of NH-37 on existing Dibrugarh-Lahoal-Chabua Bypass i.e. from Lepetketa to Kandulibari Grant Gaon section in Assam on EPCMode under NH(O)-NE (Package-1) 24.60 215.27 31-03-2022 25-07-2022 100 97 24-07-2024 09-10-2024 Ganpati Builders op.sharma0082@gmail.com, ganpatibuilders0082@gmail.com, ganpatidib@gmail.com
60 Completed Construction of 2-L Dibrugarh By Pass / realignment of NH-37 from Bogibeel Junction at km. 581.700 to km. 597.147 on EPC basis in the state of Assam under SARDP-NE 15.45 379.32 20-02-2015 02-11-2015 100 100 31-10-2018 31-10-2020 ABCI Infrastructures-JKM Pvt. Ltd (JV) jkmdbrproject@gmail.com, jkmdibrugarhbypass@gmail.com
61 Completed Widening/Improvement to 4 -Lane with Paved Shoulder from Ch. 52.470km to Ch.71.500 km (Design Ch.48.655km to Ch.67.556km)of Tulungia-Jogighopa Bridge Approach Section of Bilasipura- Guwahati road (NH 17) on EPC (Package-5) 18.90 691.53 22-03-2021 09-07-2021 99 99 31-12-2022 31-01-2024 Rajendra Singh Bhamboo Infra Pvt. Ltd. rajendrabhamboo@yahoo.co.in
62 Completed 4-Laning of NH-37 (New NH-127) from Nagaon By-pass to Teliagaon (km 278.600 to km 288.600) in the state of Assam under SARDP-NE Phase-A on EPC mode-Package-1 10.00 275.66 23-03-2020 01-07-2020 100 99 23-12-2021 09-03-2023 PRL Projects & Infra Structure Ltd. rcplassam1@gmail.com, nagaonnh127@prlinfra.com
63 Completed Widening/Improvement to 4-Lane with Paved Shoulder from km 27+701 (Simen Chapori) to km 55+000 (Nagabang Gamsuk) in Dhemaji district in the State of Assam on EPC mode under Bharatmala Pariyojna (Package-2) 27.29 562.05 31-03-2023 11-08-2023 100 100 08-02-2026 31-07-2025 Kaluwala Construction Pvt. Ltd.-Nirmal Buildinfra Pvt. Ltd. (JV) kcpl.assam@kaluwalaconstruction.in
64 Completed Construction of 4-L Jia Bharali Bridge (1.23 Km at km 26+607) along with its approaches and River Training Work from km 25.552 to km 27.500 of NH-37A (New NH-715) in the state of Assam on EPC Mode 1.94 863.49 21-12-2020 17-02-2021 98 97 05-08-2023 14-12-2023 MKC Infrastructure Ltd. - RSM Infra Projects (JV) dccindiaproject@gmail.com
65 Completed Widening/Improvement to 4-Lane with Paved Shoulder from km 81+000 to km 95+400 (Design Chainage 80+930 to 96+400) of Loring Thepi - Ganapath Gaur Gaon Section in the state of Assam under Bharatmala Pariyojana on EPC mode (Package-4) 15.47 260.07 03-02-2021 25-06-2021 96 96 17-12-2022 29-03-2023 S S Builders ssbuilderspkg4@gmail.com
66 Completed INFRASTRUCTURE WORK: Deveopment of Inland Water Transport (IWT) Terminal at MMLP Jogighopa 70.92 06-10-2021 22-04-2022 99 98 14-10-2023 31-07-2024 DVP Infra Projects Pvt. Ltd. info@dvpinfra.com
67 Completed Rehabilitation & up-gradation to 4-Lane with Paved shoulder of Dergaon Town section from Km 426.800 to Km 437.400 on NH-37(New NH-715) in Assam on EPC basis 10.60 426.15 19-03-2020 30-06-2020 100 98 19-06-2022 29-02-2024 Rajinder Infrastructure Pvt.Ltd. jornh37@gmail.com, ripl.chd@gmail.com
68 Completed Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel junction near Lapetketa ((Km. 561.700-Km. 580.875) under SARDP-NE, Phase 'A' in the State of Assam on EPC mode Pkg-I: Road works & Toll Plaza 19.17 274.34 26-07-2024 16-09-2024 100 96 14-03-2025 11-08-2025 Mohan Lal Jain mljmobohw@gmail.com
69 Completed One time improvement of Digboi to Ledo Town section (via Powal and Margherita ) of NH-38 from km 20.000 to km 53.000 in Assam on EPC Mode under NH(O) 33.00 30.84 29-07-2019 25-09-2019 100 100 23-09-2020 03-09-2020 Ganpati Builders ganpatidib@gmail.com, op.sharma0082@gmail.com, ganpatibuilders0082@gmail.com
70 Ongoing Widening/Improvement to 4 -Lane with Paved Shoulder from Ch. 88.000km to Ch.99.930 km (Design Ch.84.100km to Ch.96.000 km) of Sagunbashi forest (near Nichinta) to starting of Krishnai Bypass Section of Bilasipura Guwahati road (NH 17) on EPC (Package-7)
11.90 286.72 24-03-2023 25-10-2023 100 95 25-10-2025 12-08-2025 Mayasheel Construction msc.pkg7@gmail.com
71 Completed 4-Laning from Km 0.000 (Kaliabor Tiniali road junction) to Km 17.300 (Dolabari Road Junction) including construction of new Brahmaputra Bridge of 3.015Km (from Ch. 9+325 to Ch. 12+365) alongside of existing Kaliabhomora Bridge of NH 37-A (New NH-715) on EPC basis in the state of Assam under Phase A of SARDP-NE 17.30 843.62 31-10-2014 29-11-2014 100 100 28-11-2018 30-09-2023 Gammon India Ltd.- Satpal (S. P.) Singla construction Pvt. Ltd.[SPSCPL] (JV) manoj.rathore@gammonengineers.com, 9303_newbrahmaputra.planing@gammonengineers.com
72 Completed Widening/lmprovement to 4-Lane with paved shoulders from Km. 51+246 to Km. 66+000 (Design Chainage 50+710 Km to 65+923 Km) of Parokhuwa-Dokmoka section of NH-29 in the state of Assam under Bharatmala Pariyojana on EPC mode (Package-2) 15.21 257.50 26-03-2021 12-07-2021 89 88 03-01-2023 30-04-2023 P.D. Agrawal Infrastructure Ltd. -Apex Structure Pvt Ltd. (JV) apexcompany2009@yahoo.in
73 Completed INFRASTRUCTURE WORK: MMLP (Package-II: Building and Infrastructure works) 0.00 05-08-2020 30-09-2020 98 96 03-04-2022 25-12-2023 Credible Engineering Construction Pvt. Ltd. credibleengineering@gmail.com
74 Completed Up-gradation to 4-Laning of NH-52A from Gohpur (Km 264.100 on NH-52) to Holongi (Km.20.370 on NH-52A) in Assam on EPC under SARDP-NE 10.08 429.91 30-03-2015 11-12-2015 100 98 10-12-2018 31-10-2022 ECI Engineering & Constr. Co. Ltd. pmgohpur@eciecc.com, ecigohpur@gmail.com