| Sr. No. | Project Status | Name of Project | Length (Km) | TPC (Rs. in Cr) | Date of Award | Appointed Date | Cumulative Physical progress ( %) as Per PMIS | Cumulative Financial progress (%) as Per PMIS | Original Schedule Completion Date | Likely Date of completion | Actual Date of Completion | Name of the Contractor | Official Mail IDs of Contractor |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ongoing | Construction of 4-Lane Bridge including approaches over River Brahmaputra between Dhubri (on North Bank,Assam) and Phulbari (on south Bank,Meghalaya) on NH-127B under JICA ODA Loan assistance (Phase-III) | 19.28 | 4997.04 | 24-11-2020 | 15-12-2020 | 67 | 64 | 12-09-2028 | 12-09-2028 | Larsen & Toubro Ltd. Heavy Civil Infrastructure IC Larsen & Toubro Ltd.(L&T) | dpbplnt@gmail.com | |
| 2 | Ongoing | lmprovement to 4-Lane with Paved Shoulder from existing km 260+000 (Design Ch.4+560 km) to existing km Ch.233+000 (D. Ch.24+560) of Silchar (near Nutan Dayapur village) - Budha Nagar Section (Length-20.00 Km) of NH-37 under Package: Silchar-Jiribam Pkg-1 in the state of Assam on HAM Mode | 20.00 | 957.95 | 11-03-2024 | 15-01-2025 | 22 | 8 | 15-01-2028 | 15-01-2028 | Silchar Jiribam Highways Private Limited | headoffice@dccinfra.co.in | |
| 3 | Ongoing | Widening/lmprovement to 4-Lane with Paved Shoulder from existing road and Greenfield alignment form Design Ch. 62.800 (start of proposed Nilambazar/Cheragi Bypass) to Design Ch. 87.700 near Chandkhira Village of NH-8 on Silchar-Churaibari in the state of Assam on HAM Mode (Package-5) | 24.90 | 1258.13 | 11-03-2024 | 26-04-2025 | 0 | 0 | 23-10-2027 | 23-10-2027 | Bhartia Infra Projects Ltd | ccb_silchar@yahoo.co.in | |
| 4 | Ongoing | Widening/lmprovement to 4-Laning and Greenfield alignment with Paved shoulder of Silchar-Badarpur – Churaibari section of NH-37 & NH-8 from Design chainage 38.600 (End point of proposed Badarpur Bypass) to Km. 62.800 (Start point of proposed Nilambazar/Cheragi Bypass) in the state of Assam on HAM Mode (Package-4) | 24.20 | 1319.55 | 11-03-2024 | 18-08-2025 | 0 | 0 | 18-09-2027 | 18-09-2027 | MKC Badarpur Churaibari Kamakhya Highways Pvt. Ltd. | engineering@mkcinfrastructureltd.com | |
| 5 | Ongoing | Widening/lmprovement of Existing 2 lane to 4-Laning of Karimganj-Silchar section of NH-37 from Design Ch 0.000 near Silchar ISBT to Design Ch 15.970 near Kalinagar Pt I on NH-37 in Assam on HAM Mode (Pkg-1) | 15.97 | 1181.55 | 11-03-2024 | 17-09-2025 | 0 | 0 | 17-09-2027 | 17-09-2027 | Jandu Silchar Highway Pvt. Ltd. | jandu.panchgram@jinfratech.com | |
| 6 | Ongoing | Widening/lmprovement to 4-Lane with Paved Shoulder from Ch.5.580 Km to Ch.25.633 Km (Design Ch.0.000 Km to Ch.17.737km) (Km 901.100 to Km 921.145 of old NH-31) of Bilasipara- Guwahati road (NH-17) (Section: Near Chirakuta to near Mowatari, before Chapar Bypass) in the state ol Assam on HAM mode (Package-1) |
17.74 | 1081.15 | 11-03-2024 | 05-02-2025 | 6 | 0 | 04-08-2027 | 04-08-2027 | Bilasipara Guwahati Pvt. Ltd. | finance@bhartiainfra.com | |
| 7 | Ongoing | Widening/Improvement to 4-Lane with paved Shoulder from Ch. 25.633 Km to Ch. 52.470 Km (Design Ch. 21.850 Km to Ch.48.670 Km) for Package-2 of Bilasipura- Guwahati road (NH-17) (Section: Near Mowatari, before Chapar Bypass to Tulungia (junction with NH-17)) in the state of Assam on HAM mode under NH(O)-NE (Package-2) |
26.82 | 1338.61 | 11-03-2024 | 05-12-2024 | 4 | 0 | 03-06-2027 | 03-06-2027 | Naresh Kumar Garg Infrastructure Ltd. (NKG)-Mowatari Guwahati Road Pvt. Ltd. | nkg@nkginfra.com | |
| 8 | Ongoing | Widening/lmprovement to 4-Lane with Paved shoulder for existing as well as Greenfield alignment of Badarpur – Churaibari section of NH-8 from Design chainage 87.700 (Chandkhira) to Km. 106.500 (Churaibari) section (Assam-Tripura border) in the state of Assam on HAM Mode (Package-6) | 18.80 | 870.00 | 11-03-2024 | 07-03-2025 | 11 | 8 | 07-03-2027 | 07-03-2027 | MKC Infra Ltd.. | engineering@mkcinfrastructureltd.com | |
| 9 | Ongoing | Widening/lmprovement to 4-L of Karimgani - sutarkandi section of NH 37 from design Ch 0+020 (Start of proposed Karimganj Bypass from NH -8) to design Chainage Km 14+380 near Sutarkandi (Spur Connectivity to Indo/Bangladesh Border) on Silchar-Churaibari in the State of Assam on HAM Mode (Package-7) | 14.36 | 791.79 | 11-03-2024 | 28-02-2025 | 5 | 0 | 28-02-2027 | 28-02-2027 | MKC Infra Ltd.. | engineering@mkcinfrastructureltd.com | |
| 10 | Ongoing | Construction of 4-Lane Panchgram Bypass from Design Chainage km 15+500 on NH-37 (Old NH-53) at Kalinagar Pt.-I Village to Design Chainage km 27+300 at crossing with NH-6 (Old NH-44) Near Siddeswar Pt.-I Village on Silchar - Churaibari stretch in the State of Assam on EPC Mode under Bharatmala Pariyojana in Economic Corridors (Silchar- Churaibari Package-2) |
11.80 | 728.97 | 01-11-2023 | 10-08-2024 | 46 | 41 | 09-02-2027 | 09-02-2027 | J Infratech Limited (JIL) | isbt.silchar@jinfratech.com | |
| 11 | Ongoing | Widening/Improvement to 4-Lane with paved shoulder from Km 99+930 to Km 143+680 (Design Chainage 96+000 to 139+750) of (Paikan to Dhupdhara Sahar) of Bilasipura-Guwahati Road on NH-17 in the state of Assam on EPC mode under Bharatmala Pariyojana in Economic Corridors (Project Length – 43.750km) under NH(O)-NE (Package-8) |
43.75 | 1457.59 | 14-03-2023 | 27-12-2023 | 57 | 50 | 26-12-2026 | 25-12-2026 | YFC Projects Pvt. Ltd. - TTC Infra India (JV) | ttcii.bg.pkg8@gmail.com | |
| 12 | Ongoing | Construction of New 2-Lane Bridge with its approaches from km 0+000 to Km 4+385 across River Brahmaputra on NH-17 at Jogighopa in Assam on EPC mode |
4.38 | 746.76 | 10-08-2021 | 12-11-2021 | 73 | 71 | 10-11-2024 | 18-12-2026 | Satpal (S. P.) Singla construction Pvt. Ltd.[SPSCPL] | spsjogighopa@spsingla.com | |
| 13 | Ongoing | Widening/Improvement to 2-Lane Lane with Paved Shoulder from km 16+900 (Bogapani) to km 27+150 (Golai Goan) on existing Dibrugarh to Ledo section with proposed Digboi Bypass (Green Field and Brownfield) (2-Lane+PS) of NH-315 (OLD NH-38) in Tinsukia District under NH(O)- NE (Pkg-4) | 10.25 | 356.65 | 28-02-2023 | 08-12-2023 | 23 | 19 | 06-12-2025 | 06-12-2026 | RK Infracorp Pvt. Ltd. | rkinfradigboiproject2023@gmail.com | |
| 14 | Ongoing | Widening/Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Srirampur (near Bhairiguri Village) to Kachukhana Harichara Paglagaunj (Package-I) of Srirampur - Dhubri Section of NH-127B from existing Km 0.000 to Km 28.050 (Design Km 0.000 to Km 27.650), (Design Length=27.650 Km) under JICA ODA Loan assistance (Phase-V) -Balance work |
27.65 | 613.89 | 06-09-2024 | 25-11-2024 | 44 | 37 | 25-11-2026 | 25-11-2026 | R&C Infra Engineers Pvt. Ltd-J Infratech Limited (JIL) (JV) | rc.jandupkg1@jinfratech.com | |
| 15 | Ongoing | 4-Laning of Dhanehari Lailapur / Vairengte section from Existing Chainage km 12+920 to km 43+000 of NH 306 (Design Chainage km 20+000 to km 49+360) on Silchar - Vairengte Sairang road in the State of Assam under Bharatmala Pariyojna on EPC mode. (Project Length 29.360 km) under NH(O)-NE (Package-2) |
29.36 | 1716.21 | 31-03-2023 | 14-02-2024 | 65 | 61 | 14-08-2026 | 14-08-2026 | J Infratech Limited (JIL) | jandu.silchar@jinfratech.com | |
| 16 | Ongoing | Construction of 4-Lane Badarpur Bypass from Design Chainage km 27+300 at crossing with NH-6 (Old NH-44) Near Siddeswar Pt.-I Village to Design Chainage km 38+600 on NH-37 (Old NH-44) at Kandigram Chaita Village on Silchar - Churaibari stretch in the State of Assam on EPC Mode under Bharatmala Pariyojana in Economic Corridors (Silchar- Churaibari Pkg-3) |
11.10 | 574.26 | 16-03-2023 | 09-02-2024 | 55 | 49 | 09-08-2026 | 10-08-2026 | S S Builders | badarpurkmr@gmail.com | |
| 17 | Ongoing | 4-Laning of Silchar - Dhanehari section from Existing Chainage km 263+800 of NH 37 to km 12+920 of NH 306 (Design Chainage km 0+000 to km 20+000) on Silchar - Vairengte - Sairang road in the State of Assam under Bharatmala Pariyojna on EPC mode (Package-1) |
20.00 | 1256.90 | 21-03-2023 | 22-01-2024 | 48 | 44 | 23-07-2026 | 22-07-2026 | YFC Projects Pvt. Ltd. - TTC Infra India (JV) | ttcii.sd.pkg1@gmail.com | |
| 18 | Ongoing | Widening/ Improvement to 4-Lane with Paved Shoulder from Ch. 177+372km to Ch.203+783km (Design Ch.173+434km to Ch.200+750km) of Bilasipura- Guwahati road (NH 17) (Section: Milmila R.F (before Chayagaon Market) to Approach of Airport Junction (VIP Chowk) in the State of Assam on EPC mode under Bharatmala Pariyojana in Economic Corridors (Project Length - 27.316km) for (Package-10) |
27.31 | 1264.90 | 31-03-2023 | 18-12-2023 | 39 | 29 | 18-06-2026 | 18-06-2026 | ANIL Das - SAILAJA Commercial Construction Pvt. Ltd. (JV) | anilsailajaprojectspkg10@gmail.com | |
| 19 | Ongoing | Widening/Improvement to 4-Lane with Paved Shoulder from Ch. 143+680km to Ch.177+372km (Design Ch.139+750km to Ch.173+434km) of Bilasipura- Guwahati road on NH-17 (Section: Dhupdhara Sahar to Milmila Reserve Forest (before Chayagaon Market)) in the state of Assam on EPC mode under Bharatmala Pariyojana in Economic Corridors (Project Length –33.684km) NH(O)-NE (Package-9) |
33.68 | 1000.27 | 20-03-2023 | 11-12-2023 | 40 | 27 | 11-06-2026 | 11-06-2026 | ANIL Das - SAILAJA Commercial Construction Pvt. Ltd. (JV) | anilsailajaprojects@gmail.com | |
| 20 | Ongoing | Widening/Improvement to 4-Lane with Paved Shoulder from km 55+000 (Nagabang Gamsuk) to km 82+514 (Oyan) in the State of Assam and Arunachal Pradesh on EPC mode under Bharatmala Pariyojna of Length 27.514 Km (Package-3) | 27.51 | 665.47 | 31-03-2023 | 16-09-2024 | 73 | 66 | 17-03-2027 | 31-03-2026 | Kaluwala Construction Pvt. Ltd.-Nirmal Buildinfra Pvt. Ltd. (JV) | kcpl.assam@kaluwalaconstruction.in | |
| 21 | Ongoing | Widening/Improvement to 4-Lane with Paved Shoulder from km 626+030 (Nalani hulla Gaon) to km 650+450 (Chotahapjan) on existing Tinsukhia -Makum Bypass of NH-15 (OLD NH-37) and Strengthening of existing NH-315 (OLD NH-38) from Km 0+000 (Chotahapjan) to Km 16+900 (Bogapani section) (2-Lane +PS) in Assam on EPCMode under NH(O)-NE (Pkg-3) | 41.32 | 458.59 | 03-02-2023 | 19-05-2023 | 72 | 70 | 17-05-2025 | 31-03-2026 | TTC Infra India | ttcii.tm@gmail.com | |
| 22 | Ongoing | Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 136.500 near Hejaichak to km 156.489 near P. Leikul (Package-9) on EPC mode under NH(O)-NE (Package-9) |
19.98 | 614.43 | 31-03-2023 | 29-08-2023 | 70 | 51 | 29-08-2025 | 31-03-2026 | pc.nh137@kpc.co | pc.nh137@kpc.co | |
| 23 | Ongoing | Wideinig & Upgradation to 2-lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 96.870 near Jiri River to km 116.550 near Hangrum (Package-7) on EPC mode (Package–7) |
19.68 | 846.82 | 22-01-2024 | 04-03-2024 | 72 | 68 | 04-03-2026 | 04-03-2026 | Rajinder Infrastructure Pvt.Ltd. | official.riplassam@gmail.com | |
| 24 | Ongoing | Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 490.800 to Km 534.800, under SARDP- NE on EPC Mode in the state of Assam Pkg- IV: (Structures & Toll Plaza) | 0.00 | 100.22 | 19-08-2024 | 18-10-2024 | 49 | 43 | 13-10-2025 | 28-02-2026 | Bhardwaj Unibuild Pvt. Ltd. | bupljd4@gmail.com | |
| 25 | Ongoing | Widening & Upgradation to 2-lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 116.480 near Hangrum to km 136.500 near Hejaichak (Package-8) on EPC mode under NH(O)-NE (Package 8) |
20.02 | 904.04 | 31-03-2023 | 29-08-2023 | 69 | 60 | 29-08-2025 | 28-02-2026 | Anusha Projects Pvt. Ltd.- BKD Infrastructures Pvt. Ltd. (JV) | appl.tmr8@gmail.com | |
| 26 | Ongoing | Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 501.800 to Km 514.800 (13.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-II: Road Works) | 13.00 | 542.87 | 06-08-2024 | 10-10-2024 | 53 | 49 | 05-10-2025 | 28-02-2026 | Bharat Vanijya Eastern Pvt. Ltd.(BVEPL) | contact@bvepl.com | |
| 27 | Ongoing | Widening/Improvement to 4-Lane with Paved Shoulder from KM 38+500 to Km 51+246 (Design Chainage 38+500 to 50+959) with proposed Daboka Bypass of Daboka-Parokhaowa of NH 29 on EPC under NH(O)-NE (Package-1) |
12.46 | 516.88 | 24-02-2023 | 30-11-2023 | 91 | 90 | 29-11-2025 | 28-02-2026 | Mehta Construction Co. | mehtapkg1nh29@gmail.com | |
| 28 | Ongoing | Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 514.800 to Km 534.800 (20.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-III: Road Works) | 20.00 | 619.70 | 06-08-2024 | 03-10-2024 | 60 | 57 | 28-09-2025 | 28-02-2026 | Kaushal Sharma | ksharma.tsk@gmail.com | |
| 29 | Ongoing | Widening & Upgradation to 2 lanes with paved shoulders road from Tamenglong to Mahur (NH-137) in the State of Assam starting from km 156.489 near P. Leikul to km 176.410 near Borowapu on EPC mode under NH(O)-NE (Assam portion) (Package-10) |
19.92 | 693.15 | 31-03-2023 | 29-08-2023 | 67 | 59 | 29-08-2025 | 28-02-2026 | Anusha Projects Pvt. Ltd.- BKD Infrastructures Pvt. Ltd. (JV) | anushaprojects@gmail.com | |
| 30 | Ongoing | Widening & Improvement to 2-lane with Paved shoulder configuration of Dudhnoi - Dainadubi section (NH-217) under Bharatmala Pariyojana from design km 0+000 to km 8+415 (existing km 0+000 to km 8+600 of Old NH-62) in the State of Assam on EPC mode under NH(O)-NE, (Assam portion) | 8.41 | 88.56 | 31-03-2023 | 26-03-2024 | 77 | 72 | 25-09-2025 | 31-01-2026 | Shyama Construction | shyamaconstructionnh217@gmail.com | |
| 31 | Ongoing | Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old) from Km 453.000 to Km 490.800, under SARDP- NE , under EPC Mode in the state of Assam : Pkg-IV (Structures & Toll Plaza) | 279.01 | 15-01-2024 | 14-02-2024 | 96 | 92 | 11-08-2024 | 31-01-2026 | Sadguru Engineers & Allied Services Pvt. Ltd. | seaspvtltdghy@gmail.com | ||
| 32 | Ongoing | Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old) from Km 463.00 to Km 477.000 (14.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-II: Road Works) | 14.00 | 438.44 | 15-01-2024 | 14-02-2024 | 96 | 92 | 11-08-2024 | 31-01-2026 | Binni Construction | binniconstruction73@gmail.com | |
| 33 | Ongoing | Construction of Balance Work of 4-Laning of the Section from Jhanji to Demow of NH-37 (Old) from Km 490.800 to Km 501.800 (11.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-I: Road Works) | 11.00 | 476.50 | 06-08-2024 | 03-10-2024 | 81 | 78 | 28-09-2025 | 31-01-2026 | Regal Enterprises | regaljdpkg1@gmail.com, regal.jitender@gmail.com | |
| 34 | Ongoing | 4-Laning from Rangagara to Kaliabor Tiniali from km 297.00 to km 315.315 of NH-37 on EPC basis under SARDP-NE in state of Assam |
18.32 | 462.88 | 16-01-2017 | 23-10-2017 | 88 | 87 | 21-04-2020 | 17-01-2026 | Simplex Infrastructures Ltd. | c3172@simplexinfra.com | |
| 35 | Ongoing | Construction of Balance Work of the 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old): Pkg-III: Road Works from Km 477.000 to Km 490+800 (13.800 Km), under SARDP- NE under EPC Mode in the state of Assam | 13.80 | 358.72 | 15-01-2024 | 14-02-2024 | 99 | 99 | 11-08-2024 | 15-01-2026 | M. P. (Mahabir Prasad) Agarwala Pvt. Ltd. | mpagarwalapvtltd@gmail.com | |
| 36 | Ongoing | Construction of Balance Work of 4-Laning of the Section from Jorhat to Jhanji of NH-37 (Old) from Km 453+000 to Km 463+000 (10.000 Km), under SARDP- NE under EPC Mode in the state of Assam (Pkg-I: Road Works) | 10.00 | 478.30 | 15-01-2024 | 14-02-2024 | 97 | 93 | 11-08-2024 | 15-01-2026 | Sadguru Engineers & Allied Services Pvt. Ltd. | seaspvtltdghy@gmail.com | |
| 37 | Ongoing | Widening/lmprovement to 4-Lane with Paved Shoulder from Dillai at Km 146+230 to Lahorijan at Km 157+46O (Design Chainage 145+712 to 156+502) of Dillai - Lahorijan (Package -7) |
10.79 | 204.10 | 02-09-2022 | 20-01-2023 | 97 | 95 | 20-07-2024 | 15-01-2026 | Shankar Agarwal | nh29pkg7sa@gmail.com | |
| 38 | Completed | Widening/improvement to 4-Lane with paved shoulder from km. 606+300 to km 626+030 of NH-37 on existing Lahoal-Chabua Bypass i.e. Kandulibari Grant Gaon to Nalanihulla section in Assam on EPCMode under NH(O)-NE [Pkg-2] | 19.73 | 170.95 | 05-04-2022 | 25-07-2022 | 100 | 99 | 24-07-2024 | 22-08-2024 | Jugal Kishore Mahanta Infra works (JKM) | jkmahanta@jkminfra.net, jkmho@jiminfra.net, jkmdbrproject@gmail.com | |
| 39 | Completed | 4-Laning of Balachera-Harangjao section of NH-54 (ext.) (New NH-27) from km 275.00 to km 244.00 in the state of Assam on EPC mode under East-West corridor project under NHDP-II | 25.25 | 887.68 | 31-10-2017 | 26-12-2017 | 100 | 99 | 24-06-2020 | 15-04-2024 | Sushee Infra & Mining Limited - JSC Purpetruboprovodstroy (JSC PTPS) (JV) | planning.balachera@gmail.com | |
| 40 | Completed | Improvement and Strenghtening of Road Section from Chand Khera to Kurti Bridge on NH-208A on (Assam-Tripura Border) in the state of Assam on EPC Mode under NH(O) | 17.95 | 66.94 | 04-10-2016 | 28-11-2016 | 100 | 98 | 24-01-2018 | 31-03-2018 | Ganesh Ram Dokania | ||
| 41 | Completed | 4-Laning of NH-37 (New NH-127) from Teliagaon to Rangagara (km 288.600 to km 297.000) in the state of Assam under SARDP-NE Phase-A on EPC mode–Package-2 | 8.40 | 170.28 | 20-03-2020 | 01-07-2020 | 100 | 98 | 23-12-2021 | 30-03-2023 | Ganga Sagar Singh | support@gss.org.in | |
| 42 | Completed | 4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass from Km 182.000 to Km 208.000 of NH-52 on EPC mode in state of Assam under SARDP-NE |
26.00 | 735.17 | 13-10-2016 | 19-12-2016 | 100 | 92 | 19-06-2019 | 30-07-2025 | T.K. Engineering Consortium Pvt. Ltd. (TKECPL) | info@ganpatibharat.com | |
| 43 | Completed | Widening/lmprovement to 4-Lane of Daboka Dimapur Stretch from Km 95+400 to Km 113+830 (Design Chainage 96+400 Km to 113+830 Km) of Ganpath Gaur Gaon- Kwaram Taro Vitlage in the state of Assam under Bharatmala Pariyojana on EPC mode (Package-5) | 17.43 | 288.85 | 31-03-2021 | 12-07-2021 | 100 | 99 | 12-01-2023 | 19-11-2024 | B.K.Sons Infra Pvt. Ltd. | info@bksonsinfra.com | |
| 44 | Completed | Widening / Improvement to 4-Lane with Paved Shoulder configuration of existing single lane road from Kachukhana Harichara Paglagaunj to Dhubri - Phulbari Bridge approach (Package-II) of Srirampur - Dhubri Section of NH-127B from existing Km 28.050 to Km 55.060 (Design Km 27.650 to Km 54.154), (Design Length=26.504 Km) under JICA ODA Loan assistance (Phase-V) [Srirampur - Dhubri Pkg-2] |
26.50 | 909.02 | 04-08-2022 | 02-01-2023 | 100 | 98 | 01-01-2025 | 30-06-2025 | J Infratech Limited (JIL) | assam.pkg2@gmail.com, assam.pkg2@jinfratech.com | |
| 45 | Completed | Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel junction near Lapetketa ((Km. 561.700-Km. 580.875) under SARDP-NE, Phase 'A' in the State of Assam on EPC mode Pkg-II: Structures | 0.00 | 55.96 | 26-07-2024 | 16-09-2024 | 100 | 98 | 14-03-2025 | 12-08-2025 | Mehta Construction Co. | mccmobostr@gmail.com | |
| 46 | Completed | 2-laning with paved shoulders from km 6.25 to 10.40 including RoB (Railway Over Bridge) at Srikona Railway Level Crossing at km 9.901 of Silchar- Badarpur section of NH-53 in state of Assam under SARDP-NE | 4.15 | 76.78 | 23-03-2015 | 01-10-2015 | 100 | 98 | 11-12-2017 | 10-06-2022 | Shree Gautam Construction Company Ltd. | sgcclsilchar@gmail.com | |
| 47 | Completed | Widening/Improvement to 4-Lane with Paved Shoulder from km 0+800 (Kandulijan Gaon) to km 27+701 (Simen Chapori) of NH-515 in the State of Assam on EPC mode under Bharatmala Pariyojna (Dibrugarh-Oyan, Package-1) | 26.90 | 609.16 | 31-03-2023 | 18-10-2023 | 100 | 99 | 17-04-2026 | 11-08-2025 | Kaluwala Construction Pvt. Ltd.-Nirmal Buildinfra Pvt. Ltd. (JV) | kcpl.assam@kaluwalaconstruction.in | |
| 48 | Completed | 4-Lane highway connecting km 17.300 of old NH-37A (New NH-715) and km 182 of NH-52 (New NH-15) between Dolabari and Jamuguri Section in Assam on EPC basis under SARDP-NE, Phase-A | 16.86 | 592.01 | 05-11-2021 | 07-02-2022 | 100 | 95 | 08-08-2023 | 13-12-2023 | BN Infra Project LLP | mkcilrsmjv@gmail.com, jatin.s@rsminfra.in, jiabharali.dc@mkcinfrastructureltd.com | |
| 49 | Completed | Widening/Improvement to 4-Lane with Paved shoulder from km 66.00 to km 81.00 (Design Chainage 65.923 to 80.930) of Dokmoka - LoringThepi section- (Package-3) | 15.01 | 266.26 | 10-08-2020 | 30-09-2020 | 100 | 97 | 24-03-2022 | 27-12-2022 | Skylark Infra Engg. Pvt. Ltd. | pm.dokmoka@skylarkworld.com | |
| 50 | Completed, C.C. under issue | INFRASTRUCTURE WORK: MMLP (Pkg.-III : External Rail Connectivity) | 3.76 | 09-10-2020 | 01-12-2020 | 93 | 90 | 01-06-2022 | 20-09-2024 | Sumcon Infraventures LLP | gunjan@sumconinfraventures.com | ||
| 51 | Completed | 4-Laning of Numaligarh to Jorhat section from Km. 402.500 to Km. 453.000 (Design Km 403.200 to Km 454.240) of NH-37 except construction of Dergaon bypass from Km 426.800 to Km 437.420 (Design Km 427.400 to 438.720) | 39.72 | 1655.44 | 31-10-2014 | 23-05-2015 | 99 | 98 | 22-05-2018 | 15-03-2024 | Hindustan Construction Company (HCC) | njrp.pd@hccindia.com, njrp.qclab@hccindia.com, njrp@hccindia.com | |
| 52 | Completed | 4-Laning of NH-37 Section between Demow to End of Moran Bypass (From Km. 534.800 to Km. 561.700) including Emergency Landing Facility (ELF) under SARDP-NE, Phase 'A' in the State of Assam on EPC mode | 26.90 | 385.57 | 14-10-2022 | 20-01-2023 | 100 | 98 | 20-07-2024 | 14-07-2025 | Mohan Lal Jain | msmljaindurgapur@yahoo.com | |
| 53 | Completed | Construction and up gradation to 4-Lane of existing two lane with paved shoulder from Hapachara to Tulungia road of NH-117 of existing Km 0.00 to km 14.050 and (Design Km 0.000 to km 14.660) under BMP on EPC mode |
14.66 | 224.85 | 26-03-2020 | 26-06-2020 | 98 | 93 | 26-12-2022 | 30-06-2024 | B.K.Sons Infra Pvt. Ltd. | info@bksonsinfra.com | |
| 54 | Completed | One time improvement of Moran Town section of NH-37 from km 555.000 to km 558.500 in Assam on EPC Mode under NH(O) | 3.50 | 14.52 | 31-05-2019 | 19-08-2019 | 100 | 82 | 17-08-2020 | 31-12-2020 | BB Enterprises | binudborgohain1972@gmail.com | |
| 55 | Completed | Widening/Improvement to 4-Lane with paved shoulder from Ch.75.330Km to Ch.88.00km (Design Ch.71.800 to 84.100 km) of Jogighopa Bridge Approach (Near Pancharatna)- Agia (near Nichinta) section of Bilasipura-Guwahati road (NH-17) on EPC under BMP (Package-6) | 11.78 | 203.20 | 25-08-2020 | 26-10-2020 | 100 | 100 | 19-04-2022 | 06-07-2024 | Mayasheel Construction | msc.pkg6@gmail.com | |
| 56 | Completed | NFRASTRUCTURE WORK: MMLP (Package-I: Road and Utility Works) | 4.25 | 693.97 | 05-06-2020 | 30-09-2020 | 100 | 96 | 01-04-2022 | 30-09-2024 | RAM CHANDRA PAUL | ram_chandrapaul@yahoo.in | |
| 57 | Completed | Up-gradation to 4-Laning from end of Biswanath Chariali by-pass (Km 208.000) to Gohpur (Km 265.500) of NH-52 (New NH-15) (Total length 57.50) in the state of Assam on EPC basis Under SARDP-NE (with Toll Plaza at Ch. 219+200) |
57.50 | 1451.16 | 18-10-2021 | 11-12-2021 | 100 | 98 | 14-06-2023 | 15-12-2023 | Dhatarwal Construction Company Pvt. Ltd. | babulsayan@gmail.com, babulnath40@gmail.com, dolabari.jamuguri@gmail.com | |
| 58 | Completed | Widening/Improvement to 4-Lane with Paved Shoulder from KM 113+300 to Km 146+230 (Design Chainage 113+830 to 145+712) of Kwaram Taro Village - Dillai Section (Package-6) | 31.88 | 625.64 | 10-09-2021 | 14-07-2022 | 100 | 98 | 13-07-2024 | 31-03-2025 | Ashoka Buildcon Ltd. | ablnh29pkg6@ashokabuildcon.in | |
| 59 | Completed | Widening/improvement to 4-Lane with paved shoulder from km. 581+700 to km 606+300 of NH-37 on existing Dibrugarh-Lahoal-Chabua Bypass i.e. from Lepetketa to Kandulibari Grant Gaon section in Assam on EPCMode under NH(O)-NE (Package-1) | 24.60 | 215.27 | 31-03-2022 | 25-07-2022 | 100 | 97 | 24-07-2024 | 09-10-2024 | Ganpati Builders | op.sharma0082@gmail.com, ganpatibuilders0082@gmail.com, ganpatidib@gmail.com | |
| 60 | Completed | Construction of 2-L Dibrugarh By Pass / realignment of NH-37 from Bogibeel Junction at km. 581.700 to km. 597.147 on EPC basis in the state of Assam under SARDP-NE | 15.45 | 379.32 | 20-02-2015 | 02-11-2015 | 100 | 100 | 31-10-2018 | 31-10-2020 | ABCI Infrastructures-JKM Pvt. Ltd (JV) | jkmdbrproject@gmail.com, jkmdibrugarhbypass@gmail.com | |
| 61 | Completed | Widening/Improvement to 4 -Lane with Paved Shoulder from Ch. 52.470km to Ch.71.500 km (Design Ch.48.655km to Ch.67.556km)of Tulungia-Jogighopa Bridge Approach Section of Bilasipura- Guwahati road (NH 17) on EPC (Package-5) | 18.90 | 691.53 | 22-03-2021 | 09-07-2021 | 99 | 99 | 31-12-2022 | 31-01-2024 | Rajendra Singh Bhamboo Infra Pvt. Ltd. | rajendrabhamboo@yahoo.co.in | |
| 62 | Completed | 4-Laning of NH-37 (New NH-127) from Nagaon By-pass to Teliagaon (km 278.600 to km 288.600) in the state of Assam under SARDP-NE Phase-A on EPC mode-Package-1 | 10.00 | 275.66 | 23-03-2020 | 01-07-2020 | 100 | 99 | 23-12-2021 | 09-03-2023 | PRL Projects & Infra Structure Ltd. | rcplassam1@gmail.com, nagaonnh127@prlinfra.com | |
| 63 | Completed | Widening/Improvement to 4-Lane with Paved Shoulder from km 27+701 (Simen Chapori) to km 55+000 (Nagabang Gamsuk) in Dhemaji district in the State of Assam on EPC mode under Bharatmala Pariyojna (Package-2) | 27.29 | 562.05 | 31-03-2023 | 11-08-2023 | 100 | 100 | 08-02-2026 | 31-07-2025 | Kaluwala Construction Pvt. Ltd.-Nirmal Buildinfra Pvt. Ltd. (JV) | kcpl.assam@kaluwalaconstruction.in | |
| 64 | Completed | Construction of 4-L Jia Bharali Bridge (1.23 Km at km 26+607) along with its approaches and River Training Work from km 25.552 to km 27.500 of NH-37A (New NH-715) in the state of Assam on EPC Mode | 1.94 | 863.49 | 21-12-2020 | 17-02-2021 | 98 | 97 | 05-08-2023 | 14-12-2023 | MKC Infrastructure Ltd. - RSM Infra Projects (JV) | dccindiaproject@gmail.com | |
| 65 | Completed | Widening/Improvement to 4-Lane with Paved Shoulder from km 81+000 to km 95+400 (Design Chainage 80+930 to 96+400) of Loring Thepi - Ganapath Gaur Gaon Section in the state of Assam under Bharatmala Pariyojana on EPC mode (Package-4) | 15.47 | 260.07 | 03-02-2021 | 25-06-2021 | 96 | 96 | 17-12-2022 | 29-03-2023 | S S Builders | ssbuilderspkg4@gmail.com | |
| 66 | Completed | INFRASTRUCTURE WORK: Deveopment of Inland Water Transport (IWT) Terminal at MMLP Jogighopa | 70.92 | 06-10-2021 | 22-04-2022 | 99 | 98 | 14-10-2023 | 31-07-2024 | DVP Infra Projects Pvt. Ltd. | info@dvpinfra.com | ||
| 67 | Completed | Rehabilitation & up-gradation to 4-Lane with Paved shoulder of Dergaon Town section from Km 426.800 to Km 437.400 on NH-37(New NH-715) in Assam on EPC basis | 10.60 | 426.15 | 19-03-2020 | 30-06-2020 | 100 | 98 | 19-06-2022 | 29-02-2024 | Rajinder Infrastructure Pvt.Ltd. | jornh37@gmail.com, ripl.chd@gmail.com | |
| 68 | Completed | Construction of Balance Work of 4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel junction near Lapetketa ((Km. 561.700-Km. 580.875) under SARDP-NE, Phase 'A' in the State of Assam on EPC mode Pkg-I: Road works & Toll Plaza | 19.17 | 274.34 | 26-07-2024 | 16-09-2024 | 100 | 96 | 14-03-2025 | 11-08-2025 | Mohan Lal Jain | mljmobohw@gmail.com | |
| 69 | Completed | One time improvement of Digboi to Ledo Town section (via Powal and Margherita ) of NH-38 from km 20.000 to km 53.000 in Assam on EPC Mode under NH(O) | 33.00 | 30.84 | 29-07-2019 | 25-09-2019 | 100 | 100 | 23-09-2020 | 03-09-2020 | Ganpati Builders | ganpatidib@gmail.com, op.sharma0082@gmail.com, ganpatibuilders0082@gmail.com | |
| 70 | Ongoing | Widening/Improvement to 4 -Lane with Paved Shoulder from Ch. 88.000km to Ch.99.930 km (Design Ch.84.100km to Ch.96.000 km) of Sagunbashi forest (near Nichinta) to starting of Krishnai Bypass Section of Bilasipura Guwahati road (NH 17) on EPC (Package-7) |
11.90 | 286.72 | 24-03-2023 | 25-10-2023 | 100 | 95 | 25-10-2025 | 12-08-2025 | Mayasheel Construction | msc.pkg7@gmail.com | |
| 71 | Completed | 4-Laning from Km 0.000 (Kaliabor Tiniali road junction) to Km 17.300 (Dolabari Road Junction) including construction of new Brahmaputra Bridge of 3.015Km (from Ch. 9+325 to Ch. 12+365) alongside of existing Kaliabhomora Bridge of NH 37-A (New NH-715) on EPC basis in the state of Assam under Phase A of SARDP-NE | 17.30 | 843.62 | 31-10-2014 | 29-11-2014 | 100 | 100 | 28-11-2018 | 30-09-2023 | Gammon India Ltd.- Satpal (S. P.) Singla construction Pvt. Ltd.[SPSCPL] (JV) | manoj.rathore@gammonengineers.com, 9303_newbrahmaputra.planing@gammonengineers.com | |
| 72 | Completed | Widening/lmprovement to 4-Lane with paved shoulders from Km. 51+246 to Km. 66+000 (Design Chainage 50+710 Km to 65+923 Km) of Parokhuwa-Dokmoka section of NH-29 in the state of Assam under Bharatmala Pariyojana on EPC mode (Package-2) | 15.21 | 257.50 | 26-03-2021 | 12-07-2021 | 89 | 88 | 03-01-2023 | 30-04-2023 | P.D. Agrawal Infrastructure Ltd. -Apex Structure Pvt Ltd. (JV) | apexcompany2009@yahoo.in | |
| 73 | Completed | INFRASTRUCTURE WORK: MMLP (Package-II: Building and Infrastructure works) | 0.00 | 05-08-2020 | 30-09-2020 | 98 | 96 | 03-04-2022 | 25-12-2023 | Credible Engineering Construction Pvt. Ltd. | credibleengineering@gmail.com | ||
| 74 | Completed | Up-gradation to 4-Laning of NH-52A from Gohpur (Km 264.100 on NH-52) to Holongi (Km.20.370 on NH-52A) in Assam on EPC under SARDP-NE | 10.08 | 429.91 | 30-03-2015 | 11-12-2015 | 100 | 98 | 10-12-2018 | 31-10-2022 | ECI Engineering & Constr. Co. Ltd. | pmgohpur@eciecc.com, ecigohpur@gmail.com |